|
2024-11-21
|
36
|
Site Investigation Workplan (SIWP) Approved
|
|
DNR APPROVES OF SIWP WITH COMMENTS
|
|
2024-11-01
|
135
|
Site Investigation Workplan (SIWP) Received (fee)
|
|
WORKPLAN FOR ADD'L OFF-SITE AND ON-SITE SOIL DELINEATION, VAPOR SAMPLING, GW MONITORING, VMS INSTALL
|
|
2024-07-18
|
98
|
Technical Assistance Provided
|
|
DNR REQUESTING SI BE COMPLETED PRIOR TO ADDITIONAL REMEDIAL ACTION
|
|
2024-07-01
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2024 - 6/30/2024
|
|
2024-06-21
|
97
|
Technical Assistance Request Received (fee)
|
|
CONSULTANT REQUESTING DNR CONCURRENCE THAT ADD'L EXCAVATION IS NECESSARY
|
|
2024-04-12
|
43
|
Site Activity Status Update Received
|
|
REQUESTING OFF-SITE ACCESS FOR ADD'L SOIL BORINGS IN CITY OF GREEN BAY ROW & AT 445 S ADAMS
|
|
2024-03-26
|
43
|
Site Activity Status Update Received
|
|
CONSULTANT PLANNING TO PERFORM ADD'L EXCAVATION; DNR RECOMMENDS ADD'L DELINEATION & SIR SUBMITTAL
|
|
2024-01-05
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2023 - 12/31/2023
|
|
2023-12-14
|
364
|
VAL and/or VRSL Exceeded
|
|
|
|
2023-12-14
|
366
|
VAL and/or VRSL Exceeded at Off-Site Property or ROW
|
|
|
|
2023-07-31
|
43
|
Site Activity Status Update Received
|
|
CONSULTANT'S SECOND REQUEST TO 445 S ADAMS TO SET UP TIME TO INSTALL VMS
|
|
2023-07-12
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 01/01/2023 - 06/30/2023
|
|
2023-06-28
|
43
|
Site Activity Status Update Received
|
|
NOTIFICATION OF VAPOR SAMPLING RESULTS TO OFF-SITE PROPERTIES 445 ADAMS & 501 WASHINGTON
|
|
2023-06-21
|
99
|
Miscellaneous
|
|
RECENT VAPOR, GROUNDWATER, AND SOIL SAMPLING RESULTS; 445 S ADAMS HAS SUB-SLAB VRSL EXCEEDANCES
|
|
2023-06-20
|
43
|
Site Activity Status Update Received
|
|
RECENT VAPOR, GROUNDWATER, AND SOIL SAMPLING RESULTS; 445 S ADAMS HAS SUB-SLAB VRSL EXCEEDANCES
|
|
2023-03-20
|
99
|
Miscellaneous
|
|
BECAUSE TCE IS A CONTAMINANT OF CONCERN, DNR RECOMMENDS PASSIVE VAPOR SAMPLING
|
|
2023-03-16
|
43
|
Site Activity Status Update Received
|
|
VAPOR SAMPLING RESULTS FOR FIRE DEPT, CLINIC & RESIDENCE; NO VAL OR VRSL EXCEEDANCES
|
|
2023-01-25
|
99
|
Miscellaneous
|
|
DNR RESPONSE TO SAMPLE THE WELLS PREVIOUSLY PROPOSED FOR PFAS SAMPLING
|
|
2023-01-06
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2022 - 12/31/2022
|
|
2022-12-13
|
43
|
Site Activity Status Update Received
|
|
UPGRADIENT MANHOLE 3217 & SEWER MAIN ABANDONED; CHANGED UPGRADIENT MANHOLE LOCATION FOR VAPOR SAMPLE
|
|
2022-11-23
|
43
|
Site Activity Status Update Received
|
|
9/29/22 GW SAMPLING RESULTS, AND ASKING IF PREVIOUSLY PROPOSED PFAS SAMPLING LOCATIONS ARE ADEQUATE
|
|
2022-11-02
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
WORKPLAN FOR SANITARY VAPOR SAMPLING
|
|
2022-11-02
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
SEE AC 35 OF SAME DATE FOR APPROVAL
|
|
2022-10-21
|
43
|
Site Activity Status Update Received
|
|
REVISED ACCESS AGREEMENT REQUEST SENT TO 445 S ADAMS FOR VAPOR SAMPLING
|
|
2022-09-30
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
BRIEF WORKPLAN FOR SANITARY VAPOR SAMPLING WITH MANHOLE LOCATIONS
|
|
2022-09-28
|
43
|
Site Activity Status Update Received
|
|
SECOND REQUEST FOR ACCESS FOR VAPOR SAMPLING SENT TO 445 S ADAMS
|
|
2022-09-27
|
43
|
Site Activity Status Update Received
|
|
445 S ADAMS RETURNED VAPOR SAMPLING ACCESS AGREEMENT WITH CHANGES THAT RP IS UNWILLING TO ACCEPT
|
|
2022-08-01
|
43
|
Site Activity Status Update Received
|
|
UPDATE ON DRILLING PLANNED 8/24 & 8/25 & STATUS OF SIGNED OFF-SITE ACCESS AGREEMENTS FOR VI SAMPLING
|
|
2022-07-14
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2022 - 6/30/2022
|
|
2022-05-16
|
36
|
Site Investigation Workplan (SIWP) Approved
|
|
WORKPLAN FOR VAPOR SAMPLING, ADDITIONAL MONITORING WELLS, & SOIL SAMPLING APPROVED W/ COMMENTS
|
|
2022-04-04
|
135
|
Site Investigation Workplan (SIWP) Received (fee)
|
|
|
|
2022-01-24
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2021 - 12/31/2021
|
|
2021-12-02
|
98
|
Technical Assistance Provided
|
|
DNR RESPONSE TO TECH ASSISTANCE REQUEST STATING THAT ADDITIONAL INVESTIGATION IS NEEDED
|
|
2021-11-18
|
120
|
PFAS Sampling Completed - Actionable Levels Detected
|
|
SEE AC 97 DATED 10/18/2021 FOR PFAS SAMPLING RESULTS
|
|
2021-11-18
|
99
|
Miscellaneous
|
|
TECHNICAL ASSISTANCE VIRTUAL MEETING: DNR, FEHR GRAHAM, DON GALLO, LIBERTY MUTUAL INSURANCE
|
|
2021-11-12
|
43
|
Site Activity Status Update Received
|
|
UPDATED CROSS-SECTIONS WITH MOST RECENT EXCAVATION; INFO ON PERMEABILLITY OF SURFACE COVER
|
|
2021-10-18
|
97
|
Technical Assistance Request Received (fee)
|
|
SCHEDULE TECHNICAL ASSISTANCE MEETING
|
|
2021-10-18
|
151
|
Remedial Action (RA) Documentation Report Received (non-fee)
|
|
SEE AC 97 FOR DOCUMENTATION
|
|
2021-07-20
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2021 - 6/30/2021
|
|
2021-05-12
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
PFAS SAMPLING APPROVED WITH COMMENT TO CONSIDER ADDING MW-3R; SEE AC 35 DATED 5/6/2021 FOR DOCUMENT
|
|
2021-05-12
|
99
|
Miscellaneous
|
|
WELL CONSTRUCTION LOGS & DEVELOPMENT FORMS FOR NEW & REPLACEMENT WELLS (SEE AC 35 DATED 5/6/2021)
|
|
2021-05-06
|
43
|
Site Activity Status Update Received
|
|
POST-EXCAVATION GW SAMPLING RESULTS FROM WELL NETWORK
|
|
2021-05-06
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
UPDATE TO PFAS SAMPLING SCOPE; PROPOSE SAMPLING REPLACEMENT WELLS SMW-1R, MW-5R, MW-15, PZ-1
|
|
2021-04-06
|
130
|
DNR Regulatory Reminder Sent
|
|
VAPOR INTRUSION AND TCE REMINDER LETTER
|
|
2021-03-19
|
43
|
Site Activity Status Update Received
|
|
POST-INJECTION GW SAMPLING UPDATE; MW-22 & MW-16 WERE DRY
|
|
2021-01-12
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2020 - 12/31/2020
|
|
2020-12-16
|
43
|
Site Activity Status Update Received
|
|
EXCAVATION SIDEWALL SAMPLES - STILL SATURATED HOT SPOTS PRESENT
|
|
2020-10-27
|
130
|
DNR Regulatory Reminder Sent
|
|
DERF FUNDING STATUS LTR
|
|
2020-08-17
|
130
|
DNR Regulatory Reminder Sent
|
|
EMERGING CONTAMINANTS REMINDER LETTER
|
|
2020-08-13
|
99
|
Miscellaneous
|
|
RESPONSE TO SOIL CLEANUP STANDARDS FOR SATURATED SOIL LEFT IN EXCAVATION
|
|
2020-07-01
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2020 - 6/30/2020
|
|
2020-05-21
|
43
|
Site Activity Status Update Received
|
|
EXCAVATION SCHEDULE FOR JUNE TO AUGUST, 2020
|
|
2020-05-08
|
64
|
Inject/Infiltrate Request Approved
|
|
INFILTRATION APPROVAL FOR REMEDIAL ACTION
|
|
2020-05-04
|
99
|
Miscellaneous
|
|
SOILS WILL BE TREATED EX-SITU IN 14 ROLL-OFF BOXES, AND 28 CY OF BAM ADDED TO BASE OF EXCAVATION
|
|
2020-04-23
|
98
|
Technical Assistance Provided
|
|
CONTAINED-OUT DETERMINATION FOR DIRECT-HAUL SOIL TO LANDFILL
|
|
2020-04-20
|
97
|
Technical Assistance Request Received (fee)
|
|
REQUEST CONTAINED-OUT DETERMINATION FOR INTERVALS OF SOIL FROM EXCAVATION TO BE DIRECT-HAULED
|
|
2020-04-20
|
63
|
Inject/Infiltrate Request Received (fee)
|
|
INJECTION REQUEST TO SPRAY BAM IN BOTTOM OF EXCAVATION
|
|
2020-03-18
|
36
|
Site Investigation Workplan (SIWP) Approved
|
|
PFAS GW SAMPLING SIWP APPROVED
|
|
2020-03-11
|
147
|
Remedial Action (RA) Design Report Received (non-fee)
|
|
RAP FOR ADDITIONAL EXCAVATION
|
|
2020-03-11
|
99
|
Miscellaneous
|
|
CONTAINED OUT SOIL PROFILE AND ANALYTICAL DATA FOR 2,300 TONS OF SOIL TO BE DISPOSED OF
|
|
2020-03-04
|
135
|
Site Investigation Workplan (SIWP) Received (fee)
|
|
|
|
2020-01-02
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2019 - 12/31/2019
|
|
2020-01-02
|
99
|
Miscellaneous
|
|
REQUEST FOR PFAS SAMPLING
|
|
2020-01-02
|
116
|
PFAS Sampling Required
|
|
PFAS SAMPLING WORKPLAN DUE DATE NOT INCLUDED IN LETTER
|
|
2020-01-02
|
114
|
PFAS Scoping Statement Received
|
|
SAMPLING REQUIRED PRIOR TO CURRENT PROCESS OF SUBMTTING A SCOPING STATEMENT
|
|
2019-12-05
|
99
|
Miscellaneous
|
|
REQUEST IN-SEWER VAPOR INVESTIGATION
|
|
2019-11-19
|
43
|
Site Activity Status Update Received
|
|
GW MONITORING RESULTS FROM 6/28/2019 & SOIL SAMPLING RESULTS FOR FURTHER EXCAVATION 8/29/2019
|
|
2019-07-08
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2019 - 6/30/2019
|
|
2019-06-27
|
43
|
Site Activity Status Update Received
|
|
PLAN TO TAKE ADDT'L SOIL SAMPLES @ MOST IMPACTED SPOTS & SAMPLE GROUNDWATER ON 6/28/2019
|
|
2019-04-30
|
151
|
Remedial Action (RA) Documentation Report Received (non-fee)
|
|
|
|
2019-02-11
|
99
|
Miscellaneous
|
|
CHANGE IN PROJECT MANAGER (SCHULTZ)
|
|
2019-01-07
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2018 - 12/31/2018
|
|
2018-11-07
|
43
|
Site Activity Status Update Received
|
|
SOIL SAMPLING RESULTS & PROPOSED ADDT'L SOIL EXCAVATION ACTIVITIES
|
|
2018-07-16
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2018 - 6/30/2018
|
|
2018-05-29
|
151
|
Remedial Action (RA) Documentation Report Received (non-fee)
|
|
SOIL EXCAVATION
|
|
2018-01-26
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2017 - 12/31/2017
|
|
2017-07-28
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2017 - 6/30/2017
|
|
2017-06-02
|
288
|
DERF - Cost Reimbursement Paid
|
|
DC629 PAID $51,475.02
|
|
2017-04-10
|
43
|
Site Activity Status Update Received
|
|
STATUS UPDATED REGARDING SOIL REMOVAL ACTIVITIES
|
|
2017-04-05
|
97
|
Technical Assistance Request Received (fee)
|
|
WASTE DETERMINATION
|
|
2017-04-05
|
98
|
Technical Assistance Provided
|
|
WASTE DETERMINATION LETTER
|
|
2017-04-04
|
43
|
Site Activity Status Update Received
|
|
ANALYTICAL DATA - RETREATED BOXES
|
|
2017-03-24
|
43
|
Site Activity Status Update Received
|
|
RETREATMENT TO OCCUR THE WEEK OF MARCH 27, 2017
|
|
2017-03-20
|
99
|
Miscellaneous
|
|
DNR RESPONSE TO PROPOSED RE-TREATMENT METHOD & REVISED WASTE CONFIRMATION SAMLING PLAN
|
|
2017-03-16
|
43
|
Site Activity Status Update Received
|
|
PROPOSED RE-TREATMENT METHOD & REVISED WASTE CONFIRMATION SAMPLING PLAN
|
|
2017-02-27
|
43
|
Site Activity Status Update Received
|
|
SAMPLE RESULTS FROM TREATED BOXES
|
|
2017-02-21
|
43
|
Site Activity Status Update Received
|
|
ANALYTICAL DATA FROM ROLL OFF BOXES
|
|
2017-01-31
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2016 - 12/31/2016
|
|
2017-01-31
|
99
|
Miscellaneous
|
|
REQUEST FOR 30-DAY EXTENSION TO STORE HAZARDOUS WASTE APPROVED
|
|
2017-01-30
|
43
|
Site Activity Status Update Received
|
|
REQUEST FOR 30-DAY EXTENSION TO STORE HAZARDOUS WASTE
|
|
2017-01-26
|
43
|
Site Activity Status Update Received
|
|
SOIL EXCAVATION ACTIVITIES WRAPPING UP
|
|
2017-01-18
|
43
|
Site Activity Status Update Received
|
|
REVISED WASTE SAMPLING PLAN
|
|
2017-01-12
|
99
|
Miscellaneous
|
|
ESTIMATED REMAINING DERF BUDGET, RECOMMENDED CHANGES TO WASTE SAMPLING PLAN
|
|
2017-01-11
|
99
|
Miscellaneous
|
|
WHS PROJECT CLEARANCE FOR BR-0137
|
|
2017-01-10
|
43
|
Site Activity Status Update Received
|
|
APPLICATION FOR PROPOSED GROUND DISTURBANCE OF BR-0137
|
|
2017-01-08
|
218
|
DERF - Cost Reimbursement Application Approved
|
|
DC-629 APPROVED
|
|
2017-01-03
|
43
|
Site Activity Status Update Received
|
|
WASTE SAMPLING PLAN
|
|
2016-12-15
|
99
|
Miscellaneous
|
|
HAZARDOUS WASTE SAMPLING STORAGE, SAMPLING & TREATMENT APPROACH
|
|
2016-12-13
|
43
|
Site Activity Status Update Received
|
|
HAZARDOUS WASTE SAMPLING
|
|
2016-12-12
|
99
|
Miscellaneous
|
|
REQUEST OF SAMPLE DATA IN TABLE FORMAT
|
|
2016-12-12
|
43
|
Site Activity Status Update Received
|
|
WASTE DETERMINATION
|
|
2016-12-12
|
43
|
Site Activity Status Update Received
|
|
SAMPLE DATA
|
|
2016-12-12
|
43
|
Site Activity Status Update Received
|
|
SAMPLING APPROACH
|
|
2016-12-09
|
43
|
Site Activity Status Update Received
|
|
TREATED SOIL DATA
|
|
2016-12-09
|
43
|
Site Activity Status Update Received
|
|
WASTE DETERMINATION CLARIFICATION
|
|
2016-12-08
|
43
|
Site Activity Status Update Received
|
|
UPDATE REGARDING SOIL REMEDIATION ACTIVITIES
|
|
2016-12-08
|
99
|
Miscellaneous
|
|
COMPACTED GRAVEL SURFACE IN AREA OF EXCAVATION ACCEPTABLE, MW-1 INSTALLED AT BASE OF EXCAVATION
|
|
2016-12-07
|
43
|
Site Activity Status Update Received
|
|
UPDATE REGARDING SOIL REMEDIATION ACTIVITIES
|
|
2016-11-11
|
43
|
Site Activity Status Update Received
|
|
DEMOLITION TO OCCUR THE WEEK OF NOVEMBER 28, 2016
|
|
2016-10-13
|
99
|
Miscellaneous
|
|
APPROVAL TO UTILIZE UP TO $15,000 IN DERP FUNDS (SUBCONTRACTOR COSTS) FOR BUILDING DEMOLITION
|
|
2016-10-05
|
112
|
DERF - Change Order Received
|
|
REQUEST FOR UP TO $15,000 FOR BUILDING DEMOLITION COSTS
|
|
2016-09-15
|
147
|
Remedial Action (RA) Design Report Received (non-fee)
|
|
REVISED RAP
|
|
2016-08-16
|
64
|
Inject/Infiltrate Request Approved
|
|
|
|
2016-08-10
|
63
|
Inject/Infiltrate Request Received (fee)
|
|
|
|
2016-08-10
|
43
|
Site Activity Status Update Received
|
|
WPDES PERMIT FOR SOIL MIXING & TREATMENT
|
|
2016-07-11
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2016 - 6/30/2016
|
|
2016-06-24
|
43
|
Site Activity Status Update Received
|
|
DRILLING TO TAKE PLACE JUNE 28 & 29, 2016
|
|
2016-05-03
|
40
|
Remedial Action Options Report (RAOR) Approved
|
|
|
|
2016-04-21
|
43
|
Site Activity Status Update Received
|
|
REVISED DERP COST ESTIMATE FOR RA
|
|
2016-04-20
|
43
|
Site Activity Status Update Received
|
|
VARIANCE REQUEST FOR CONSULTANT/RA BIDDING. UPDATED DERF COST ESTIMATE FOR RA.
|
|
2016-02-26
|
39
|
Remedial Action Options Report (RAOR) Received (non-fee)
|
|
REVISED WORK PLAN & COST ESTIMATE FOR REMAINING SCOPE OF WORK
|
|
2016-01-11
|
217
|
DERF - Cost Reimbursement Application Received
|
|
|
|
2016-01-07
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2015 - 12/31/2015
|
|
2015-10-14
|
98
|
Technical Assistance Provided
|
|
DNR RESPONSE
|
|
2015-08-13
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER MONITORING DATA
|
|
2015-07-27
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2015 - 6/30/2015
|
|
2015-07-07
|
97
|
Technical Assistance Request Received (fee)
|
|
|
|
2015-01-21
|
99
|
Miscellaneous
|
|
EMULSIFIED VEG OIL REACTION TIME FRAME ENDS 11/2015, THEN START POST-INJECTION/REMEDIATION GW MNTING
|
|
2015-01-20
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2014 - 12/31/2014
|
|
2015-01-20
|
43
|
Site Activity Status Update Received
|
|
ON-SITE BLDG IS VACANT. EXPECTED REACTION TIME FOR EMULSIFIED VEGETABLE OIL IS ~ 2 YRS
|
|
2015-01-16
|
99
|
Miscellaneous
|
|
REQUEST FOR ADDT'L INFORMATION THAT PERTAINS TO 10/28/2014 SUBMITTAL
|
|
2014-10-28
|
43
|
Site Activity Status Update Received
|
|
SUMMARY OF ADDT'L SCOPE OF WORK
|
|
2014-09-17
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2014 - 6/30/2014
|
|
2014-07-14
|
99
|
Miscellaneous
|
|
REQUEST FOR CASE STATUS UPDATE
|
|
2014-01-30
|
130
|
DNR Regulatory Reminder Sent
|
|
DERF FUNDING STATUS LTR
|
|
2013-02-28
|
99
|
Miscellaneous
|
|
RA CHANGE ORDER #5 APPROVED; RA CHANGE ORDER #4 RESCINDED
|
|
2012-10-23
|
99
|
Miscellaneous
|
|
REQUEST FOR MODIFIED COST ESTIMATE FOR 06-28-2012 CHANGE ORDER
|
|
2012-06-28
|
112
|
DERF - Change Order Received
|
|
|
|
2012-02-01
|
218
|
DERF - Cost Reimbursement Application Approved
|
|
DERF RA7 APPROVED, CHECK BEING PROCESSED
|
|
2012-01-18
|
64
|
Inject/Infiltrate Request Approved
|
|
|
|
2012-01-18
|
99
|
Miscellaneous
|
|
INJECTION PERMIT AND WPDES PERMIT
|
|
2012-01-05
|
63
|
Inject/Infiltrate Request Received (fee)
|
|
$500 CK044212 ARCADIS
|
|
2011-11-01
|
217
|
DERF - Cost Reimbursement Application Received
|
|
RA CLAIM #8
|
|
2011-09-08
|
130
|
DNR Regulatory Reminder Sent
|
|
Vapor Intrusion (VI) Assessment Notification Ltr Sent
|
|
2011-07-07
|
99
|
Miscellaneous
|
|
RA CHANGE ORDER #4 APPROVED
|
|
2011-06-07
|
43
|
Site Activity Status Update Received
|
|
REVISED COST ESTIMATE SUBMITTED
|
|
2011-03-09
|
99
|
Miscellaneous
|
|
REQUEST FOR ADDITIONAL INFORMATION REGARDING CHANGE ORDER #4
|
|
2011-03-01
|
112
|
DERF - Change Order Received
|
|
RA CHANGE ORDER #4
|
|
2011-02-11
|
43
|
Site Activity Status Update Received
|
|
WORK SCOPE BEING REVIEWED BY ATTORNEY & RP. WILL THEN BE SUBMITTED TO DNR UPON ATTY & RP APPROVAL.
|
|
2011-02-10
|
99
|
Miscellaneous
|
|
REQUEST FOR CASE UPDATE
|
|
2010-02-08
|
99
|
Miscellaneous
|
|
PROCEED WITH INSTALLATION OF WELL NEST AND PIEZOMETER
|
|
2010-02-02
|
43
|
Site Activity Status Update Received
|
|
MAP DEPICTING LOCATION OF PROPOSED WELL NEST AND PIEZOMETER
|
|
2009-10-08
|
99
|
Miscellaneous
|
|
RA CHANGE ORDER #3 APPROVED
|
|
2009-10-01
|
112
|
DERF - Change Order Received
|
|
RA CHANGE ORDER #3
|
|
2009-09-10
|
218
|
DERF - Cost Reimbursement Application Approved
|
|
CLAIM DC-319 AUDITED (ORIGINALLY RCVD 6/30/09). SINCE FUNDS AVAILABLE NOW, CHECK WILL BE SENT ASAP.
|
|
2009-08-25
|
99
|
Miscellaneous
|
|
DERF REIMBURSEMENT CHECK FOR RA # 6 (DC-302 RCVD MAR 2009) MAILED TODAY
|
|
2009-07-08
|
99
|
Miscellaneous
|
|
REQUEST FOR CLARIFICATION REGARDING 06-30-09 DERP REIMBURSEMENT REQUEST
|
|
2009-06-30
|
217
|
DERF - Cost Reimbursement Application Received
|
|
|
|
2009-06-29
|
80
|
Closure Not Recommended
|
|
ADD'L MW/PZ INSTALLATION, VAPOR & GW MONITORING, ASSESS UTILITIES, CONSIDER ADD'L REMEDIATION
|
|
2009-06-16
|
218
|
DERF - Cost Reimbursement Application Approved
|
|
AUDIT OF RA #6 (3/09) COMPLETE. REIMB CHECK NOT YET SENT, NO FUNDS AVAILABLE. WILL BE ISSUED ASAP.
|
|
2009-05-12
|
79
|
Case Closure Review Request Received
|
|
|
|
2009-05-12
|
700
|
Database Fee Paid for Groundwater Continuing Obligation(s)
|
|
|
|
2009-05-12
|
710
|
Database Fee Paid for Soil Continuing Obligation(s)
|
|
|
|
2009-03-06
|
217
|
DERF - Cost Reimbursement Application Received
|
|
|
|
2008-09-15
|
99
|
Miscellaneous
|
|
CHECK ISSUED TODAY FOR CLAIM RCVD 9/5/07 (5TH RA CLAIM)
|
|
2007-12-07
|
218
|
DERF - Cost Reimbursement Application Approved
|
|
CLAIM #6 OVERALL, AUDIT COMPLETE, REIMB CHECK NOT YET SENT (NO FUNDS AVAIL) CHECK WILL BE SENT ASAP
|
|
2007-09-07
|
99
|
Miscellaneous
|
|
INJECTION ACTIVITIES TO END. ENTERING LONG-TERM MONITORING PHASE
|
|
2007-09-05
|
217
|
DERF - Cost Reimbursement Application Received
|
|
6TH PARTIAL RA CLAIM
|
|
2007-09-05
|
43
|
Site Activity Status Update Received
|
|
INJECTION UPDATE
|
|
2007-08-29
|
99
|
Miscellaneous
|
|
REQUEST FOR STATUS UPDATE FROM CONSULTANT
|
|
2007-08-29
|
43
|
Site Activity Status Update Received
|
|
STATUS UPDATE & DERF REIMBURSEMENT CLAIM TO BE SUBMITTED IN THE NEAR FUTURE
|
|
2006-07-06
|
112
|
DERF - Change Order Received
|
|
|
|
2006-07-06
|
112
|
DERF - Change Order Received
|
|
|
|
2006-02-13
|
217
|
DERF - Cost Reimbursement Application Received
|
|
|
|
2005-05-04
|
217
|
DERF - Cost Reimbursement Application Received
|
|
|
|
2005-03-14
|
43
|
Site Activity Status Update Received
|
|
INJECTION UPDATE
|
|
2005-01-25
|
43
|
Site Activity Status Update Received
|
|
INJECTION & MONITORING ACTIVITIES CONTINUING
|
|
2004-10-29
|
218
|
DERF - Cost Reimbursement Application Approved
|
|
AUTO-POPULATED BY CAOS
|
|
2004-10-22
|
43
|
Site Activity Status Update Received
|
|
IN THE PROCESS OF PREPARING A STATUS UPDATE
|
|
2004-08-04
|
217
|
DERF - Cost Reimbursement Application Received
|
|
|
|
2004-05-24
|
99
|
Miscellaneous
|
|
APPROVAL W/CONDITIONS TO MOVE AHEAD WITH SUPPLEMENTAL RA ACTIVITIES.
|
|
2004-05-03
|
112
|
DERF - Change Order Received
|
|
SUPPLEMENTAL RA ACTIVITIES
|
|
2003-11-25
|
43
|
Site Activity Status Update Received
|
|
GW MONITORING DATA
|
|
2003-10-03
|
218
|
DERF - Cost Reimbursement Application Approved
|
|
AUTO-POPULATED BY CAOS
|
|
2003-09-08
|
99
|
Miscellaneous
|
|
REIMBURSEMENT REQUEST FORWARDED TO CF
|
|
2003-09-05
|
217
|
DERF - Cost Reimbursement Application Received
|
|
REIMBURSEMENT RQUEST RECEIVED
|
|
2003-09-04
|
43
|
Site Activity Status Update Received
|
|
QTLY GW SAMPLES WILL BE COLLECTED IN SEPT. REIMB. REQ. BEING SENT TO DNR
|
|
2003-08-06
|
43
|
Site Activity Status Update Received
|
|
RA PROGRESS REPORT
|
|
2003-05-12
|
43
|
Site Activity Status Update Received
|
|
RQT FOR TEMP. INJECTION OF REMEDIAL MATERIAL TO ENHANCE IN-SITU GW REMEDIATION
|
|
2003-03-20
|
99
|
Miscellaneous
|
|
DNR SIGN OFF ON SSRCL APPROVAL REQUEST & SOIL DISPOSAL FOR PARKING LOT AREA
|
|
2003-03-19
|
43
|
Site Activity Status Update Received
|
|
CONSULT.RQT FOR APPROVAL OF SSRCL'S& DISPOSAL OF PARKING LOT SOIL AS NON-HAZ WASTE
|
|
2003-02-24
|
43
|
Site Activity Status Update Received
|
|
ADDITIONAL INFORMAITON FOR RA COST ESTIMATE
|
|
2003-02-24
|
99
|
Miscellaneous
|
|
APPROVAL OF RP'S CONSULTANT SELECTION FOR RA ACTIVITIES
|
|
2003-02-18
|
99
|
Miscellaneous
|
|
TELEPHONE CALL. CLARIFICATION OF ITEMS IN 02/13/03 SUBMITTAL
|
|
2003-02-13
|
43
|
Site Activity Status Update Received
|
|
ADDITIONAL INFORMATION FOR RA COST ESTIMATE
|
|
2003-01-27
|
99
|
Miscellaneous
|
|
REQUEST FOR ADDITIONAL INFORMATION FROM LOW COST BIDDER
|
|
2002-12-05
|
43
|
Site Activity Status Update Received
|
|
ADDITIONAL INFORMATION REGARDING HAZARDOUS WASTE DETERMINATION
|
|
2002-10-30
|
99
|
Miscellaneous
|
|
RQT FOR ADDITIONAL SSRCL & PROPERTY ZONING INFORMATION
|
|
2002-10-22
|
43
|
Site Activity Status Update Received
|
|
HAZARDOUS WASTE DETERMINATION & SSRCL'S
|
|
2002-09-19
|
43
|
Site Activity Status Update Received
|
|
WP & COST ESTIMATE FOR COMPLETING HAZ WASTE DETERMINATION & SSRCLS'S
|
|
2002-09-19
|
112
|
DERF - Change Order Received
|
|
WASTE DETERMINATION
|
|
2002-08-27
|
218
|
DERF - Cost Reimbursement Application Approved
|
|
AUTO-POPULATED BY CAOS
|
|
2002-08-22
|
99
|
Miscellaneous
|
|
RQT FOR ADDITIONAL INFO RE: WASTE DETERMINATION. RA BIDS PUT ON HOLD
|
|
2002-07-18
|
113
|
DERF - Bid Review Request Received
|
|
CONSULTANT BIDS FOR REMEDIAL ACTION
|
|
2002-06-07
|
217
|
DERF - Cost Reimbursement Application Received
|
|
DERF REIMBURSEMENT APPLICATION FOR SI
|
|
2002-03-27
|
146
|
Remedial Action Plan Go Ahead (Notice to Proceed)
|
|
|
|
2002-03-25
|
39
|
Remedial Action Options Report (RAOR) Received (non-fee)
|
|
REVISED ROAR
|
|
2002-03-08
|
82
|
Remedial Action Options Report (RAOR) Not Approved
|
|
|
|
2002-02-18
|
39
|
Remedial Action Options Report (RAOR) Received (non-fee)
|
|
|
|
2001-12-06
|
112
|
DERF - Change Order Received
|
|
DRUM DISPOSAL
|
|
2001-12-05
|
38
|
Site Investigation Report (SIR) Approved
|
|
|
|
2001-11-27
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
|
|
2001-10-09
|
43
|
Site Activity Status Update Received
|
|
ADDITIONAL SI COMPLETE - DNR SHOULD HAVE COPY W/I 30 DAYS
|
|
2001-06-27
|
43
|
Site Activity Status Update Received
|
|
SUMMARY OF ANTICIPATED SOIL & GW SAMPLING ACTIVITIES
|
|
2001-06-21
|
43
|
Site Activity Status Update Received
|
|
COPY OF REQUEST FOR ACCESS TO INSTALL WELLS & GEOPROBES ON CITY PROPERTY
|
|
2001-06-18
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
WITH CONDITIONS
|
|
2001-06-11
|
110
|
DERF - Potential Claim Form Approved
|
|
SOLVENT INVESTIGATION; POTENTIAL DERF SITE
|
|
2001-06-04
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
|
|
2001-06-04
|
112
|
DERF - Change Order Received
|
|
SITE INVESTIGATION ACTIVITIES
|
|
2001-05-09
|
140
|
Site Investigation Report (SIR) Not Approved
|
|
ADD. SOIL & GW DEFINITION NEEDED BEFORE PROCEEDING W/RA
|
|
2001-05-07
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
|
|
2001-03-28
|
43
|
Site Activity Status Update Received
|
|
WILL BE INSTALLING ADDITIONAL WELLS WEEK OF 03/26/01
|
|
2001-02-02
|
43
|
Site Activity Status Update Received
|
|
RQT TO CITY OF GB FOR APPROVAL TO INSTALL OFF-SITE WELLS IN ROW
|
|
2001-01-18
|
36
|
Site Investigation Workplan (SIWP) Approved
|
|
|
|
2001-01-16
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
|
|
2001-01-16
|
112
|
DERF - Change Order Received
|
|
SITE INVESTIGATION ACTIVITIES
|
|
2000-10-30
|
37
|
Site Investigation Report (SIR) Received (non-fee)
|
|
|
|
2000-08-14
|
36
|
Site Investigation Workplan (SIWP) Approved
|
|
|
|
2000-08-10
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
|
|
2000-08-01
|
43
|
Site Activity Status Update Received
|
|
UPDATE ON ADDITIONAL SI ACTIVITIES
|
|
2000-06-29
|
36
|
Site Investigation Workplan (SIWP) Approved
|
|
|
|
2000-06-27
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
|
|
2000-01-06
|
2
|
Responsible Party (RP) letter sent
|
|
|
|
1999-12-21
|
64
|
Inject/Infiltrate Request Approved
|
|
|
|
1999-12-16
|
1
|
Notification of Hazardous Substance Discharge
|
|
|
|
1999-12-16
|
63
|
Inject/Infiltrate Request Received (fee)
|
|
|