02-05-514372
1404 S WEBSTER AVE
|
Activity Type / Status | Jurisdiction |
---|---|
ERP / OPEN | DNR RR |
Location Name | County | DNR Region |
---|---|---|
ECONO-CARE CLEANERS | BROWN | NORTHEAST |
Address | Municipality |
---|---|
1404 S WEBSTER AVE | ALLOUEZ VIL |
PLSS Description | Latitude (WGS84) | Longitude (WGS84) | Google Maps | RR Sites Map |
---|---|---|---|---|
NW 1/4 of the SE 1/4 of Sec 01, T23N, R20E | 44.4933399 | -88.0164177 |
![]() |
![]() |
Additional Activity Details | Acres |
---|---|
Electronic Only - No Hard File | UNKNOWN |
Facility ID | PECFA No. | EPA ID | Start Date | End Date |
---|---|---|---|---|
405008340 | 2003-04-14 |
Above Ground Petrol Tank |
Drycleaner |
EPA NPL Site |
EPA Superfund |
PECFA Funds Eligible |
PFAS |
ROW Impact |
Sediments |
Underground Petrol Tank |
WI DOT Site |
---|---|---|---|---|---|---|---|---|---|
![]() |
![]() |
Name | File |
---|---|
SITE_FILE_2003_Thru_Jan_2013 | ![]() |
Date | Code | Name | File | Comment | |
---|---|---|---|---|---|
2025-01-23 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2024 - 6/30/2024 | |
2024-11-27 | 43 | Site Activity Status Update Received |
![]() |
OCTOBER 2024 GROUNDWATER MONITORING RESULTS | |
2024-11-27 | 120 | PFAS Sampling Completed - Actionable Levels Detected | SEE AC43 OF SAME DATE FOR DOCUMENTATION | ||
2024-08-19 | 36 | Site Investigation Workplan (SIWP) Approved |
![]() |
APPROVAL OF SUPPLEMENTAL SI FOR ADDITIONAL SOIL AND GW INVESTIGATION; COMMENTS ON VAPOR AND PFAS | |
2024-07-24 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2024 - 6/30/2024 | |
2024-07-23 | 135 | Site Investigation Workplan (SIWP) Received (fee) |
![]() |
WORKPLAN FOR FURTHER SOIL AND GW DELINEATION AND GW MONITORING | |
2024-02-19 | 99 | Miscellaneous |
![]() |
RECOMMEND ADDITIONAL SOIL AND GW DELINEATION, CREATE CSM & SUBMIT EC SCOPING | |
2024-01-24 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2023 - 12/31/2023 | |
2023-10-12 | 37 | Site Investigation Report (SIR) Received (non-fee) |
![]() |
||
2023-07-26 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 01/01/2023 - 06/30/2023 | |
2023-06-09 | 99 | Miscellaneous |
![]() |
RECOMMEND ADDITIONAL SOIL AND GROUNDWATER DELINEATION | |
2023-06-02 | 43 | Site Activity Status Update Received |
![]() |
APRIL 2023 ON-SITE AND OFF-SITE GROUNDWATER MONITORING RESULTS | |
2023-04-25 | 43 | Site Activity Status Update Received |
![]() |
UPDATE FROM THE CONSULTANT THAT THEY WILL BE PERFORMING GROUNDWATER MONITORING THIS WEEK | |
2023-01-26 | 43 | Site Activity Status Update Received |
![]() |
PASSIVE SAMPLING RESULTS SENT TO OFF-SITE RESIDENCES & ON-SITE BUSINESS; NO VAL OR VRSL EXCEEDANCE | |
2023-01-12 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2022 - 12/31/2022 | |
2022-11-14 | 99 | Miscellaneous |
![]() |
CONSULTANT REQUESTING ACCESS TO 1410 S WEBSTER FOR A SECOND ROUND OF VAPOR SAMPLING | |
2022-11-14 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) | VERBAL CONVERSATION WITH CONSULTANT PROVIDING DNR'S NOTICE TO PROCEED WITH VAPOR SAMPLING | ||
2022-11-08 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) |
![]() |
PLAN TO PASSIVE SAMPLE IN HOMES AND SANITARY; SOURCE FOR TCE FOUND IN BASEMENT OF 930 DERBY | |
2022-11-07 | 43 | Site Activity Status Update Received |
![]() |
AUGUST 2022 SOIL SAMPLING RESULTS AND SEPTEMBER 2022 GW SAMPLING RESULTS AND DRAFT FIGURES | |
2022-11-02 | 99 | Miscellaneous |
![]() |
DNR REQUESTING RESAMPLING OF 930 S DERBY AND SUBMITTAL OF WORKPLAN ASAP | |
2022-09-19 | 99 | Miscellaneous |
![]() |
RECOMMENDED NEXT STEPS FOR VAPOR SAMPLING WITHIN BUILDINGS AND SANITARY SEWER | |
2022-09-12 | 43 | Site Activity Status Update Received |
![]() |
VAPOR SAMPLING RESULTS NOTIFICATION FOR 930 DERBY LN; INDOOR AIR IN BASEMENT ABOVE VAL FOR TCE | |
2022-08-24 | 43 | Site Activity Status Update Received |
![]() |
NOTIFICATION OF VI SAMPLING RESULTS FOR 1404 S WEBSTER & 926 DERBY - BELOW VALS AND VRSLS | |
2022-08-01 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) |
![]() |
NOTICE TO PROCEED WITH COMMENTS FOR DELINEATION IN ADDITIONAL DIRECTIONS AS GW MAY FLOW RADIALLY | |
2022-07-22 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) |
![]() |
WORKPLAN TO INSTALL SOIL BORING AND MONITORING WELLS TO FURTHER DELINEATE SOIL & GW ON & OFF-SITE | |
2022-07-18 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2022 - 6/30/2022 | |
2022-05-26 | 43 | Site Activity Status Update Received |
![]() |
926 DERBY LANE VAPOR SAMPLING RESULTS; NO SUB-SLAB VRSL OR INDOOR AIR VAL EXCEEDANCES | |
2022-03-23 | 43 | Site Activity Status Update Received |
![]() |
VAPOR SAMPLING RESULTS FOR RESIDENCES & ON-SITE BUILDING; DNR RESPONSE | |
2022-01-21 | 99 | Miscellaneous |
![]() |
ACCESS AGREEMENTS SENT FOR VAPOR SAMPLING @ 1324, 1404 & 1410 S WEBSTER; 926 930 DERBY LN | |
2022-01-19 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) |
![]() |
WORKPLAN FOR ON-SITE & OFF-SITE VAPOR SAMPLING, SANITORY VAPOR INVESTIGATION & GW MONITORING | |
2022-01-19 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) | SEE AC 35 OF SAME DATE FOR NOTICE TO PROCEED | ||
2022-01-11 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2021 - 12/31/2021 | |
2021-11-09 | 43 | Site Activity Status Update Received |
![]() |
RESPONSE UPCOMING TO THE INITIAL SCOPE; NO WORK PERFORMED YET | |
2021-09-30 | 7 | Environmental Consultant Hired |
![]() |
ENVIRONFORENSICS HIRED; INSURANCE IS FUNDING WORK | |
2021-09-21 | 43 | Site Activity Status Update Received |
![]() |
DHS 5-DAY PASSIVE VAPOR SAMPLING RESULTS FROM 1324S WEBSTER; NON DETECT FOR PCE & TCE | |
2021-09-02 | 43 | Site Activity Status Update Received |
![]() |
1324 S WEBSTER YOU ARE MY SUNSHINE DAY CARE VAPOR SAMPLING RESULTS BELOW STANDARDS | |
2021-08-23 | 99 | Miscellaneous |
![]() |
L AMUNDSON (RP) NOT ALLOWING ACCESS FOR DHS TO SAMPLE INDOOR AIR AT ON-SITE BUILDING AT THIS TIME | |
2021-08-17 | 35 | Site Investigation Workplan (SIWP) Received (non-fee) |
![]() |
ABBREVIATED WORKPLAN FOR VAPOR SAMPLING @ 1324 S WEBSTER | |
2021-08-17 | 30 | Site Investigation Workplan (SIWP) Notice to Proceed (NTP) | DNR NOTICE TO PROCEED WITH COMMENTS FOR VAPOR SAMPLING @ 1324 S WEBSTER (SEE AC 35 FOR DOCUMENT) | ||
2021-07-27 | 99 | Miscellaneous |
![]() |
DNR RESPONSE TO VAPOR SAMPLING QUESTIONS FOR DAYCARE @ 1324 S WEBSTER | |
2021-07-01 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2021 - 6/30/2021 | |
2021-06-07 | 99 | Miscellaneous |
![]() |
DNR REQUESTS UPDATE;RESPONSE WITH INSURANCE UPDATE & ADDITIONAL INFO | |
2021-04-06 | 130 | DNR Regulatory Reminder Sent |
![]() |
VAPOR INTRUSION AND TCE REMINDER LETTER | |
2021-01-07 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2020 - 12/31/2020 | |
2020-10-27 | 130 | DNR Regulatory Reminder Sent |
![]() |
DERF FUNDING STATUS LTR | |
2020-08-17 | 130 | DNR Regulatory Reminder Sent |
![]() |
EMERGING CONTAMINANTS REMINDER LETTER | |
2020-07-10 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2020 - 6/30/2020 | |
2020-05-07 | 99 | Miscellaneous |
![]() |
LETTERS TO 1404, 1410 & 1320 S WEBSTER AVE & 930 & 926 DERBY LN FOR SCREENING DEMOGRAPHICS | |
2020-05-07 | 99 | Miscellaneous |
![]() |
COMPLIANCE ASSISTANCE RESPONSE | |
2020-05-04 | 99 | Miscellaneous |
![]() |
CONSULTATION WITH DHS FOR COVID-19 COMPLIANCE ASSISTANCE RQUEST | |
2020-04-30 | 99 | Miscellaneous |
![]() |
COMPLIANCE ASSISTANCE REQUESTED | |
2020-03-30 | 43 | Site Activity Status Update Received |
![]() |
ADDITIONAL SOIL BORINGS DID NOT CONFIRM SHALLOW SOIL CONTAMINATION @ 1324 S WEBSTER | |
2020-03-13 | 29 | Phase II Environmental Site Assessment (ESA) Rpt Received |
![]() |
PHASE II FOR 1324 S WEBSTER USING WAM GRANT FUNDS; CONTAMINATION IN SOIL & GROUNDWATER | |
2020-02-14 | 99 | Miscellaneous |
![]() |
EXTENSION TO DEADLINE TO SUBMIT VI SIWP | |
2020-01-17 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2019 - 12/31/2019 | |
2020-01-14 | 99 | Miscellaneous | REQUEST FOR VAPOR SAMPLING ON-SITE & AT ADJACENT PROPERTIES | ||
2020-01-14 | 99 | Miscellaneous |
![]() |
REQUEST FOR VAPOR INVESTIGATION | |
2019-11-11 | 43 | Site Activity Status Update Received | DRAFT GW & SOIL SAMPLING RESULTS FROM WAM FUNDING PHASE II PERFORMED @ 1324 S WEBSTER | ||
2019-10-14 | 99 | Miscellaneous |
![]() |
VI INVESTIGATION RECOMMENDATIONS FOR REDEVELOPMENT @ AFFECTED OFF-SITE - 1324 S WEBSTER AVE | |
2019-07-24 | 99 | Miscellaneous |
![]() |
OFF-SITE CONTAMINATION CLOSURE NOTIFICATIONS SENT IN ERROR. | |
2019-07-18 | 28 | Phase I Environmental Site Assessment (ESA) Rpt Received |
![]() |
PHASE I FOR 1324 S WEBSTER USING WAM GRANT FUNDS | |
2019-07-10 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2019 - 6/30/2019 | |
2019-04-12 | 37 | Site Investigation Report (SIR) Received (non-fee) |
![]() |
SIR ASSOCIATED WITH LUST CASE @ SAME PROPERTY, INCLUDES CVOC SAMPLING DATA | |
2019-02-11 | 99 | Miscellaneous |
![]() |
CHANGE IN PROJECT MANAGER (SCHULTZ) | |
2019-01-24 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2018 - 12/31/2018 | |
2018-08-07 | 99 | Miscellaneous |
![]() |
RESPONSE TO SAMPLING REQUEST | |
2018-07-06 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2018 - 6/30/2018 | |
2018-07-03 | 43 | Site Activity Status Update Received |
![]() |
GROUNDWATER REQUEST | |
2015-07-07 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2015 - 6/30/2015 | |
2015-01-08 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 7/1/2014 - 12/31/2014 | |
2014-09-22 | 195 | Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met |
![]() |
Period: 1/1/2014 - 6/30/2014 | |
2014-04-28 | 99 | Miscellaneous | DISCUSSED PECFA AND DERF OPTIONS WITH RP | ||
2014-01-30 | 130 | DNR Regulatory Reminder Sent | DERF FUNDING STATUS LTR | ||
2013-01-23 | 38 | Site Investigation Report (SIR) Approved | |||
2013-01-22 | 37 | Site Investigation Report (SIR) Received (non-fee) | |||
2012-09-13 | 99 | Miscellaneous | LETTER SENT - NEW PROJECT MANAGER WILL BE BOB KLAUK | ||
2011-09-08 | 130 | DNR Regulatory Reminder Sent |
![]() |
Vapor Intrusion (VI) Assessment Notification Ltr Sent | |
2011-07-06 | 43 | Site Activity Status Update Received | RP WRITTEN RESPONSE - UPDATE | ||
2010-05-18 | 99 | Miscellaneous | REQUEST FOR CASE STATUS | ||
2010-05-18 | 43 | Site Activity Status Update Received | NOT ABLE TO TO THE WORK | ||
2008-08-29 | 110 | DERF - Potential Claim Form Approved | |||
2008-06-10 | 200 | Push Action Taken | REQUEST FOR STATUS UPDATE | ||
2004-04-21 | 43 | Site Activity Status Update Received | DATA FROM ADJACENT #03-05-002199 | ||
2004-04-02 | 99 | Miscellaneous | DNR LTR REQUESTING STATUS OF INVESTIGATION | ||
2004-01-12 | 43 | Site Activity Status Update Received | LTR FROM RP - NO MONEY - CHECKING W/CONSULTANT ON OPTIONS | ||
2003-12-12 | 99 | Miscellaneous | DNR LTR CONFIRMING TELEPHONE CONVERSATION OF 12/11/2003 | ||
2003-12-11 | 43 | Site Activity Status Update Received | TEL. CONVERSATION WITH RP, WIFE SHOULD HAVE RP LETTER AT HOME. | ||
2003-12-08 | 43 | Site Activity Status Update Received | CERT. MAIL RP LETTER SIGNED FOR | ||
2003-12-01 | 2 | Responsible Party (RP) letter sent | 2ND RP LETTER SENT VIA CERTIFIED MAIL | ||
2003-10-20 | 2 | Responsible Party (RP) letter sent | |||
2003-06-19 | 43 | Site Activity Status Update Received | OWNERSHIP & PROPERTY USE HISTORY | ||
2003-05-08 | 99 | Miscellaneous | 2ND PRP LETTER - CERTIFIED MAIL | ||
2003-04-15 | 20 | Potential Responsible Party (PRP) Letter Sent | |||
2003-04-14 | 1 | Notification of Hazardous Substance Discharge | PRP LETTER SENT 4/15/03 |
Substance | Type | Amt Released | Units |
---|---|---|---|
Chlorinated Solvents | VOC | ||
Per- and Polyfluoroalkyl Substances (PFAS ADDED FROM AC120) | Industrial Chem | ||
Trichloroethylene | Industrial Chem |
LEE AMUNDSON 6426 NERO RD, SOBIESKI, WI 54171 |
MARK AMUNDSON 6426 NERO ROAD, SOBIESKI, WI 54171 |
JOSIE SCHULTZ josie.schultz@wisconsin.gov |