2024-07-09
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2024 - 6/30/2024
|
|
2024-01-08
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2023 - 12/31/2023
|
|
2023-07-05
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 01/01/2023 - 06/30/2023
|
|
2023-01-03
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2022 - 12/31/2022
|
|
2022-07-05
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2022 - 6/30/2022
|
|
2022-03-30
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
|
|
2022-03-30
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
|
|
2021-04-06
|
130
|
DNR Regulatory Reminder Sent
|
|
VAPOR INTRUSION AND TCE REMINDER LETTER
|
|
2020-08-17
|
130
|
DNR Regulatory Reminder Sent
|
|
EMERGING CONTAMINANTS REMINDER LETTER
|
|
2020-07-01
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2020 - 6/30/2020
|
|
2020-01-02
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2019 - 12/31/2019
|
|
2019-07-01
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2019 - 6/30/2019
|
|
2019-01-02
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2018 - 12/31/2018
|
|
2018-05-17
|
2
|
Responsible Party (RP) letter sent
|
|
|
|
2018-01-26
|
351
|
Superfund Site Assessment Site Inspection (SI)
|
|
FINAL SI RPT OF AFFF AREAS
|
|
2017-11-21
|
1
|
Notification of Hazardous Substance Discharge
|
|
|
|
2016-08-18
|
99
|
Miscellaneous
|
|
FINAL QAPP ADDENDUM FIELD SAMPLING PLAN
|
|
2016-03-28
|
99
|
Miscellaneous
|
|
FINAL QAPP FOR SI OF AFFF AREAS - MULTIPLE
|
|
2015-12-01
|
350
|
Superfund Site Assessment Preliminary Assessment (PA)
|
|
FINAL PRELIM ASSESSMENT RPT FOR PFAS
|
|
2015-12-01
|
120
|
PFAS Sampling Completed - Actionable Levels Detected
|
|
SEE AC 350 OF SAME DATE FOR DOCUMENTATION
|