2024-07-02
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLING RESULTS
|
|
2024-07-01
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2024 - 6/30/2024
|
|
2024-04-18
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER, SOIL, INDOOR AIR AND SUB-SLAB VAPOR SAMPLING RESULTS
|
|
2024-01-22
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2023 - 12/31/2023
|
|
2023-12-15
|
43
|
Site Activity Status Update Received
|
|
SOIL, GROUNDWATER, SUB-SLAB VAPOR & INDOOR AIR SAMPLING RESULTS
|
|
2023-10-30
|
43
|
Site Activity Status Update Received
|
|
NOTIFICATION OF SOIL, GROUNDWATER, SUB-SLAB VAPOR & INDOOR AIR RESULTS TO DNR & PROPERTY OWNER
|
|
2023-09-21
|
30
|
Site Investigation Workplan (SIWP) Notice to Proceed (NTP)
|
|
ADDITIONAL GROUNDWATER, SUB-SLAB VAPOR & INDOOR AIR SAMPLING
|
|
2023-08-21
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
ADDITIONAL GROUNDWATER, SUB-SLAB VAPOR & INDOOR AIR SAMPLING
|
|
2023-07-19
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 01/01/2023 - 06/30/2023
|
|
2023-06-15
|
2
|
Responsible Party (RP) letter sent
|
|
POSSESSOR RP LETTER
|
|
2023-05-15
|
140
|
Site Investigation Report (SIR) Not Approved
|
|
ADDITIONAL GROUNDWATER, VAPOR AND INDOOR AIR SAMPLING REQUIRED
|
|
2023-05-01
|
118
|
PFAS Sampling Not Required At This Time
|
|
|
|
2023-03-23
|
137
|
Site Investigation Report (SIR) Received (fee)
|
|
|
|
2023-03-23
|
114
|
PFAS Scoping Statement Received
|
|
SEE AC 137 OF SAME DATE FOR DOCUMENTATION
|
|
2023-03-23
|
28
|
Phase I Environmental Site Assessment (ESA) Rpt Received
|
|
SEE AC 137 OF SAME DATE FOR DOCUMENTATION
|
|
2023-01-17
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2022 - 12/31/2022
|
|
2022-12-04
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLING RESULTS; SIR ANTICIPATED TO BE SUBMITTED
|
|
2022-08-24
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLING RESULTS
|
|
2022-07-22
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2022 - 6/30/2022
|
|
2022-04-04
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLING RESULTS
|
|
2022-01-24
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2021 - 12/31/2021
|
|
2022-01-07
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER & VAPOR SAMPLING RESULTS
|
|
2021-09-13
|
43
|
Site Activity Status Update Received
|
|
GROUNDWATER SAMPLING RESULTS; PER DISCUSSION WITH CONSULTANT MORE WORK NEEDED TO COMPLETE SIR
|
|
2021-07-07
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2021 - 6/30/2021
|
|
2021-07-01
|
43
|
Site Activity Status Update Received
|
|
SOIL, GROUNDWATER AND VAPOR SAMPLING RESULTS
|
|
2021-04-06
|
130
|
DNR Regulatory Reminder Sent
|
|
VAPOR INTRUSION AND TCE REMINDER LETTER
|
|
2021-01-25
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 7/1/2020 - 12/31/2020
|
|
2020-09-04
|
99
|
Miscellaneous
|
|
REQUEST FOR ADDITIONAL INFORMATION INCLUDING EMERGING CONTAMINANT SCOPING (VIA EMAIL)
|
|
2020-08-17
|
130
|
DNR Regulatory Reminder Sent
|
|
EMERGING CONTAMINANTS REMINDER LETTER
|
|
2020-08-12
|
35
|
Site Investigation Workplan (SIWP) Received (non-fee)
|
|
ELECTRONIC COPY ONLY
|
|
2020-08-03
|
7
|
Environmental Consultant Hired
|
|
PSI (ELECTRONIC COPY)
|
|
2020-07-23
|
195
|
Semi-Annual/PECFA Cost Reporting (NR700) Requirement Met
|
|
Period: 1/1/2020 - 6/30/2020
|
|
2020-02-19
|
2
|
Responsible Party (RP) letter sent
|
|
|
|
2020-02-07
|
1
|
Notification of Hazardous Substance Discharge
|
|
SITE ASSESSMENT 7/16/2019
|
|
2020-02-07
|
29
|
Phase II Environmental Site Assessment (ESA) Rpt Received
|
|
|