Reporting Period: | 7/1/2016 - 12/31/2016 |
BRRTS No: | 02-16-562899 |
Activity Name: | FRASER SHIPYARDS - PUNCH SHED BUILDING |
Status: | Site Investigation |
Activity: | Field Sampling/Monitoring |
Comments: | On October 20, 2016 ET submitted a Request for Technical Assistance regarding completion of delineation. On November 15, 2016, Chris Saari from the WDNR responded that limited additional soil contamination delineation was needed and groundwater monitoring to document attenuation. The groundwater monitoring wells were sampled on January 10, 2017 and we're awaiting results. Soil delineation is planned to be completed in the spring of 2017. |
Submitted by John McCarthy on 01/11/2017 |