Comments: |
Activities performed during first half of 2014:
1. Completed and submitted Downgradient Investigation Summary Report, dated February 14, 2014;
2. Installed and sampled one additional piezometer at a downgradient location;
3. Conducted quarterly groundwater monitoring; and
4. Began preparation of the Site Investigation Report
Activities planned for upcoming 6-month period:
1. Complete and submit the Site Investigation Report;
2. Prepare and submit the Remedial Action Options Report; and
3. Continue quarterly groundwater monitoring.
|