ENVIRONMENTAL CLEANUP & BROWNFIELDS REDEVELOPMENT
NR700 ACTIVITY PROGRESS REPORT

Reporting Period: 1/1/2017 - 6/30/2017
BRRTS No: 02-41-560089
Activity Name: MID-AMERICA STEEL DRUM COMPANY INC/KITZINGER
Status: Site Investigation
Activity: Field Sampling/Monitoring
Comments: A work plan was submitted to WDNR on 4/24/2017 for department review and approval. The work plan is intended to move forward toward delineating the horizontal and vertical extent of soil and groundwater hydrocarbon impacts at the site. On 6/5/2017, WDNR issued it's review of the work plan and requested additional information. Currently, a response to the WDNR's 6/5/2017 letter is in progress. Following WDNR approval, additional investigation activity will be completed.
Submitted by Kurt McClung on 08/08/2017