ENVIRONMENTAL CLEANUP & BROWNFIELDS REDEVELOPMENT
NR700 ACTIVITY PROGRESS REPORT

Reporting Period: 1/1/2018 - 6/30/2018
BRRTS No: 02-41-553761
Activity Name: WABASH ALLOYS
Status: Site Investigation
Activity: Field Sampling/Monitoring
Comments: Beazer did not have any reports during this period. Beazer submitted a Revised Supplemental Site Investigation Work Plan to DNR on June 4, 2018. Connell did not have any reports during this period. Connell is awaiting a letter approving a completed NR 716 Site Investigation for Connell's responsible contaminants (PCBs & metals) and a response to the 2 questions regarding the wetlands capping and the revision to the RAOR, emailed November 22, 2017.
Submitted by Mike Noel on 07/13/2018