Reporting Period: | 1/1/2018 - 6/30/2018 |
BRRTS No: | 02-16-000475 |
Activity Name: | MAGELLAN PIPELINE |
Status: | Remediation |
Activity: | Closure Request Package Preparation |
Comments: | The following deliverables were submitted to the WDNR during the reporting period: 01-2018: Request to Modify Groundwater Sampling Program (request to remove clean side-gradient wells MW-5 and MW-8 from quarterly closure sampling program) 05-2018: Project Status Update No. 3 (Summary of 1st Quarter 2018 groundwater monitoring results and request for WDNR concurrence that site closure process may proceed) |
Submitted by Jennifer Shelton on 07/20/2018 |