ENVIRONMENTAL CLEANUP & BROWNFIELDS REDEVELOPMENT
NR700 ACTIVITY PROGRESS REPORT

Reporting Period: 7/1/2018 - 12/31/2018
BRRTS No: 03-06-001296
Activity Name: MARUM, JOHN PROPERTY
Status: Remediation
Activity: Sampling/Monitoring
Comments: A remedial excavation was completed in August 2018. Approximately 671.6 tons of impacted soil was removed. Monitoring wells MW-6, -7, -8, -9 (inside remedial excavation) were installed in August 2018. The wells were sampled September 12 and December 10, 2018. The monitoring well network elevations were re-surveyed. Ground water levels were measured during each sampling event. The results and our recommendations will be submitted to the DNR in a report in the next month.
PECFA Cost Est: $15000
Submitted by Ken Shimko on 01/02/2019