Comments: |
A Project Status Update was submitted to WDNR on June 12, 2019. After several months of no response from WDNR a meeting was requested to discuss the project. At that time we were notified that the assigned project manager was being transferred to another WDNR department and that a new project manager was going to be assigned. A meeting was held with the new project manager on December 4, 2019 at which time some additional impact delineation work was requested including two additional monitoring wells and an expanded soil vapor intrusion study area including 17 new residences and an apartment complex. An Additional Site Investigation Work Plan was submitted to WDNR on December 13, 2019.
|