Reporting Period: | 7/1/2014 - 12/31/2014 |
BRRTS No: | 03-55-000408 |
Activity Name: | DOUGS TIRE (FORMER) |
Status: | Remediation |
Activity: | Active Remediation |
Comments: | A Soil Vapor Extraction Pilot test was completed in May 2014. Based on the Pilot Test measurements, a Remedial Action Plan with cost estimates, bids, construction diagrams was submitted in July 2014. DNR made numerous comments in August. A revised Plan was submitted in DRAFT form in September. DNR rejected the DRAFT version requesting a signed report. We will re-submit a signed Plan in early 2015. |
PECFA Cost Est: | $100000 |
Submitted by Kenneth Shimko on 01/06/2015 |