Reporting Period: | 7/1/2020 - 12/31/2020 |
BRRTS No: | 02-42-578125 |
Activity Name: | FORT MCCOY FIRE TRAINING BURN PIT #3 PFAS |
Status: | Site Investigation |
Activity: | Report Preparation |
Comments: | Fort McCoy has completed review of the Revised Final Draft Report for the PA/SI work. The Final Report is expected early this year and will be forwarded to the WDNR when it is received. The report concludes that an RI/FS will be required for this site. The Army plans to retain a contractor for conducting the RI/FS and beginning this work during 2021. |
Submitted by Craig Bartholomew on 01/05/2021 |