ENVIRONMENTAL CLEANUP & BROWNFIELDS REDEVELOPMENT
NR700 ACTIVITY PROGRESS REPORT

Reporting Period: 7/1/2020 - 12/31/2020
BRRTS No: 02-36-545108
Activity Name: MIRRO PLT 9 (FORMER) - LGU
Status: Remediation
Activity: Sampling/Monitoring
Comments: Ramboll, on behalf of Newell Operating Company (NOC), has submitted two documents to the WDNR. The Site Investigation Work Plan (SIWP) was submitted on October 14, 2020 and incorporates the previously submitted PFAS Groundwater Investigation Work Plan submitted on July 14, 2020. The SIWP was approved on November 11, 2020 and field work was initiated on December 7, 2020 with a site and utility survey. The baseline groundwater sampling event was completed the week of December 14, 2020. The remaining SIWP tasks are scheduled for 2021.
Submitted by Paul Lindquist on 01/28/2021