Reporting Period: | 1/1/2021 - 6/30/2021 |
BRRTS No: | 02-08-587108 |
Activity Name: | HARP DOWNSTREAM OF HAYTON MILLPOND DAM |
Status: | Site Investigation |
Activity: | Field Sampling/Monitoring |
Comments: | Significant source removal and restoration efforts have been completed upstream and received No Further Action determinations. The additional site investigation scope, review and approval is ongoing. Reports Submitted: Site Investigation Work Plan, Revision 1, January 14, 2021 Quality Assurance Project Plan, January 14, 2021 Site Investigation Work Plan, Revision 2, June 9, 2021 Quality Assurance Project Plan, Revision 1, June 9, 2021 |
Submitted by Chris Harvey on 07/06/2021 |