ENVIRONMENTAL CLEANUP & BROWNFIELDS REDEVELOPMENT
NR700 ACTIVITY PROGRESS REPORT

Reporting Period: 1/1/2021 - 6/30/2021
BRRTS No: 02-05-586429
Activity Name: GP BROADWAY MILL EXPANSION - PFAS
Status: Site Investigation
Activity: Report Preparation
Comments: - Execution of the PFAS Site Investigation Work Plan (Dated 12/17/2020) took place the week of April 12, 2021 with the installation of eight additional groundwater monitoring wells, groundwater sample collection from eleven monitoring wells and soil sample collection from the installation of the new eight monitoring wells. - Groundwater monitoring results were submitted on 5/24/2021. - Groundwater monitoring results report was amended to include the soil sampling results and that was submitted on 6/10/2021. - The site investigation summary report is being drafted and reviewed. Anticipate submission of this report in July 2021.
Submitted by Melissa Mrotek on 07/20/2021