ENVIRONMENTAL CLEANUP & BROWNFIELDS REDEVELOPMENT
NR700 ACTIVITY PROGRESS REPORT

Reporting Period: 1/1/2021 - 6/30/2021
BRRTS No: 02-38-580694
Activity Name: JCI/TYCO FTC (PFAS)
Status: Site Investigation
Activity: Field Sampling/Monitoring
Comments: A Response to DNR comments on the Revised Long-Term Potable Well Sampling Plan was submitted on January 12. A Response to DNR Comments on the May 26, 2020, Conceptual Site Model was submitted on January 12. A Response to DNR Comments on the May 15, 2020, Interim Site Investigation Report was submitted on January 12. A Q4 2020 Project Status report was submitted on January 15. Ditch A/B Monthly WPDES Report (December 2020) were submitted on January 21. A Sample Results Notification for pond surface water samples was submitted on January 21. A Sample Results Notification for Ditch B surface water samples was submitted on February 3. A Fourth Quarter 2020 Foam Monitoring Interim Action Report and Work Plan for Future Foam Monitoring was submitted on February 15. Ditch A/B Monthly WPDES Report (January 2021) were submitted on February 21. A Remedial Action Design Report for the Groundwater Extraction and Treatment System was submitted on February 26. Semi-Annual Operation, Maintenance, and Optimization Progress Reports (January 1 through June 30, 2020) for Ditch A and Ditch B (two reports) were submitted on March 3. A Soil Interim Action Design Report was submitted on March 15. A Response to DNR Comments on the Draft Quality Assurance Project Plan was submitted on March 16. A Revised Long-Term Potable Well Sampling Plan was submitted on March 16. A Request for Secretary Preston Cole to support a water line and the provision of permanent clean water to people of the Town of Peshtigo was submitted on March 17. Ditch A/B Monthly WPDES Report (February 2021) were submitted on March 21. A Letter from JCI to the DNR Secretary Requesting a Facilitator to Advance Water Service to Town of Peshtigo was submitted on April 14. A Q1 2021 Project Status report was submitted on April 15. A Revised Foam Monitoring Work Plan was submitted on April 15. Ditch A/B Monthly WPDES Report (March 2021) were submitted on April 21. An Air Pathway Site Investigation Work Plan was submitted on April 23. Ditch A/B Monthly WPDES Report (April 2021) were submitted on May 21. A Thank you Letter to Secretary Preston Cole for expressing support for a Third-Party Facilitator was submitted on June 11. A Sample Results Notification for Ditch B surface water samples was submitted on June 18. Ditch A/B Monthly WPDES Report (May 2021) were submitted on June 21. Updates to Groundwater isoconcentration Map and Cross Section were submitted on June 23. The site investigation work is ongoing. The Long-Term Potable Well Monitoring Plan is ongoing. Bottled water and/or Point-of-Entry Treatment (POET) systems have been offered to affected potable well owners within the private drinking water well investigation area. The Ditch A and Ditch B Surface Water, Groundwater Extraction and Treatment System, Soil, and Foam Interim Actions continued or began implementation during the reporting period. Routine communications were completed with the WDNR regarding the interim action and site investigation activities.
Submitted by Ben Verburg on 07/30/2021