Reporting Period: | 7/1/2021 - 12/31/2021 |
BRRTS No: | 02-31-564071 |
Activity Name: | ALLYN PROPERTY |
Status: | Site Investigation |
Activity: | Field Sampling/Monitoring |
Comments: | In Q3 and Q4 of 2021, there were multiple activities occurring at the site. In Q3 a Site status update was submitted to the WDNR discussing the results of the Q2 vapor sampling update. Additionally in Q3, a groundwater sampling event occurred, followed by a Site Status Update submittal in Q4. A work plan is presently drafted and awaiting review and approval from the client. The SIWP is anticipated to be submitted in early Q1, 2022. |
Submitted by Christopher Rogers on 01/06/2022 |