Reporting Period: | 7/1/2021 - 12/31/2021 |
BRRTS No: | 02-08-587108 |
Activity Name: | HARP DOWNSTREAM OF HAYTON MILLPOND DAM |
Status: | Site Investigation |
Activity: | Field Sampling/Monitoring |
Comments: | Significant source removal and restoration efforts have been completed upstream and received No Further Action determinations. The additional site investigation scope, review and approval is ongoing. Reports Submitted: Response to Comments and Site Investigation Work Plan, Revision 3, December 23, 2021 Quality Assurance Project Plan, Revision 2, December 23, 2021 |
Submitted by Chris Harvey on 01/06/2022 |