ENVIRONMENTAL CLEANUP & BROWNFIELDS REDEVELOPMENT
NR700 ACTIVITY PROGRESS REPORT

Reporting Period: 7/1/2021 - 12/31/2021
BRRTS No: 02-41-582725
Activity Name: 128TH PFAS INVESTIGATION
Status: Site Investigation
Activity: No Activity
Comments: ANG is preparing to submit for public comment the Relative Risk Site Assessment (RRSE). The RRSE is used by the Air Force to rank, prioritize and sequence funding. The RRSE will be out for a 30-day public comment period in January 2022. The PFAS site is also being reviewed the Secretary of Air Force , Installations, Energy, and Environment for Defense Environmental Restoration Program (DERP) funding eligibility. Once the site is DERP eligible the regulators will be eligible to participate in the Defense State Memorandum of Agreement (DSMOA).
Submitted by William Myer on 01/13/2022