ENVIRONMENTAL CLEANUP & BROWNFIELDS REDEVELOPMENT
NR700 ACTIVITY PROGRESS REPORT

Reporting Period: 7/1/2021 - 12/31/2021
BRRTS No: 02-38-587281
Activity Name: MARINETTE MARINE BLDG 34
Status: Site Investigation
Activity: Field Sampling/Monitoring
Comments: On August 31, 2021, the WDNR approved the Site Investigation Work Plan for this Site. It was anticipated the start of site investigation activities was to be completed in two phases due to site construction activities. The first phase to occur in October 2021 and second phase in March 2022. One report summarizing all site investigation activities would be submitted in May/June 2022. However, site investigation activities have been delayed due to continued and expanded construction activities across the site. It is anticipated to have full site access in late March or early April. Both the originally proposed Phase I and II SI activities will now be completed at the same time.
Submitted by Andrew Mott on 01/24/2022