Progress concerning BRRTS #02-13-587341 for the semi-annual period from 7/1/2021 through 12/31/2021 includes the following:
- Groundwater sampling and monitoring of the existing well network in July.
- Development, submission, and approval of an interim action workplan in July.
- Development, submission, and approval of a supplemental site investigation workplan in August.
- Development and submission of a site investigation report in September.
- Execution of the supplemental site investigation and installation of five multiport monitoring wells onsite from October through December.
- Initiation of site preparation activities for interim action construction in October through December.
- Removal and disposal of fire suppression system and legacy AFFF and replacement with a new system and vendor specified fluorine-free AFFF in December.
|