ENVIRONMENTAL CLEANUP & BROWNFIELDS REDEVELOPMENT
NR700 ACTIVITY PROGRESS REPORT

Reporting Period: 1/1/2022 - 6/30/2022
BRRTS No: 02-05-586429
Activity Name: GP BROADWAY MILL EXPANSION - PFAS
Status: Site Investigation
Activity: Field Sampling/Monitoring
Comments: - Site investigation work plan #3 for this investigation was submitted on January 26, 2022. - Phase 1 of the work plan was executed the week of May 2, 2022, which included the installation of four additional groundwater monitoring wells, collection of soil samples from those well installations, and collection of groundwater samples from existing groundwater monitoring network. - Soil sample results were received June 29, 2022 and groundwater sample results were received July 8, 2022. - Facility submitted analytical results of soil and groundwater on July 14, 2022. - Facility is currently preparing site investigation summary report for the work completed in May 2022, and is preparing to execute Phase 2 of the work plan, which is another round of groundwater monitoring.
Submitted by Melissa Mrotek on 07/27/2022