ENVIRONMENTAL CLEANUP & BROWNFIELDS REDEVELOPMENT
NR700 ACTIVITY PROGRESS REPORT

Reporting Period: 7/1/2022 - 12/31/2022
BRRTS No: 02-46-000743
Activity Name: LIME KILN PARK - GRAFTON VIL
Status: Site Investigation
Activity: Field Sampling/Monitoring
Comments: The SIWP Addendum submitted on 7/1/22 included 2022 routine groundwater sampling results and responses to items referenced in WDNR's 3/2/22 letter. Sampling in the second half of 2022 included one round of vapor sampling per the 2021 SIWP on 8/16-19/22, additional private well sampling per the SIWP Addendum on 8/17/22, and geoprobe soil sampling per the 2021 SIWP on 11/18/22. Results were provided to WDNR and property owners as required. Proposed work in first quarter 2023 includes installation/sampling of water table wells and a second round of vapor sampling per the 2021 SIWP.
Submitted by Alia Enright on 01/03/2023