Reporting Period: | 7/1/2022 - 12/31/2022 |
BRRTS No: | 02-08-587108 |
Activity Name: | HARP DOWNSTREAM OF HAYTON MILLPOND DAM |
Status: | Site Investigation |
Activity: | Field Sampling/Monitoring |
Comments: | Significant source removal and restoration efforts have been completed upstream and received No Further Action determinations. The additional site investigation scope, review and approval is ongoing. Reports: Response to Comments and Site Investigation Work Plan, Revision 4, September 30, 2022 Quality Assurance Project Plan, Revision 3, September 30, 2022 |
Submitted by Chris Harvey on 01/23/2023 |