Comments: |
An NR 716 Site Investigation Work Plan was submitted to WDNR on October 4, 2022. The Work Plan proposes to install two soil borings and monitoring wells. An addendum to the work plan was submitted to describe surface water sampling, which was not described in the text but intended for inclusion. The Work Plan approval was received, with the requirement to install a third soil boring and monitoring well and an indication that WDNR will require monitoring to establish trends. The field investigation is currently being scheduled to incorporate the expanded scope. An email will be sent notifying WDNR of the field investigation schedule.
|