ENVIRONMENTAL CLEANUP & BROWNFIELDS REDEVELOPMENT
NR700 ACTIVITY PROGRESS REPORT

Reporting Period: 1/1/2023 - 6/30/2023
BRRTS No: 02-38-580694
Activity Name: JCI/TYCO FTC (PFAS)
Status: Site Investigation
Activity: Field Sampling/Monitoring
Comments: A Q4 2022 Project Status report was submitted on January 13. A Response to PWSA Deep Well Design Plan and Deep Aquifer LTM Plan was submitted on January 19. Ditch A/B and GETS Monthly WPDES Reports (December 2022) were submitted on January 21. A 2022 Foam Monitoring Interim Action Report was submitted on February 14. Fish Tissue and Surface Water Sampling Results were submitted on February 17. Ditch A/B and GETS Monthly WPDES Reports (January 2023) were submitted on February 21. A GETS Startup Monitoring – Report 10 was submitted on March 20. 3. Ditch A/B and GETS Monthly WPDES Reports (February 2023) were submitted on March 21. A Revised Long-Term Potable Well Sampling Plan was submitted on April 3. A Site Investigation Status Report was submitted on April 3. A Q1 2023 Project Status report was submitted on April 17. Ditch A/B and GETS Monthly WPDES Reports (March 2023) were submitted on April 21. A Semi-Annual Operation, Maintenance, and Optimization Progress Reports (July 1 through December 30, 2023) #7 for Ditch B was submitted on April 28. A Semi-Annual Operation, Maintenance, and Optimization Progress Reports (July 1 through December 31, 2023) #8 for Ditch A was submitted on April 28. A Quality Assurance Project Plan (QAPP) was submitted on May 1. Ditch A/B and GETS Monthly WPDES Reports (April 2023) were submitted on May 21. A GETS Operation Maintenance and Monitoring Plan was submitted on May 23. A GETS Short Term Monitoring – Report 1 was submitted on June 15. A GETS Interim Remedial Action Construction Documentation Report was submitted on June 16. Ditch A/B and GETS Monthly WPDES Reports (May 2023) were submitted on June 21. A Technical Assistance Meeting Request was submitted on June 26. The site investigation work is ongoing. The Long-Term Potable Well Monitoring Plan is ongoing. regarding within the private drinking water well investigation area. The Ditch A and Ditch B Surface Water, Groundwater Extraction and Treatment System, and Foam Interim Actions continued or began implementation during the reporting period. Routine communications were completed with the WDNR regarding the interim action and site investigation activities.
Submitted by Ben Verburg on 07/21/2023