Comments: |
- Received approval for interim action remedial construction report.
- Completed installation of the additional groundwater monitoring wells in the supplemental site investigation workplan addendum.
- Conducted a site visit with the WDNR of the remedial actions and observed well installations in April. Jointly conducted a cap maintenance inspection.
- Sampled the stormwater basin for PFAS.
- Allowed groundwater monitoring wells to equilibrate after installation and conducted groundwater monitoring well sampling of the entire well network in June.
|