Reporting Period: | 1/1/2023 - 6/30/2023 |
BRRTS No: | 02-05-586429 |
Activity Name: | GP BROADWAY MILL EXPANSION - PFAS |
Status: | Site Investigation |
Activity: | No Activity |
Comments: | - The Site Investigation Summary Report (SISR) submitted on November 11, 2022 identified the next steps for the site investigation, which included another round of groundwater monitoring in Quarter 3, 2023 approximately one year after the last groundwater monitoring event in 2022 (week of August 1, 2022). Therefore, no activity was completed in the January 1 - June 30, 2023 timeframe. |
Submitted by Melissa Mrotek on 07/26/2023 |