Site Activity Status Update on 2023-05-09
Site Activity Status Update on 2023-02-16
The site investigative wastes have been disposed of by GFL.
Last round of groundwater sampling was conducted on 4/6/2023.
Four rounds of groundwater quality data are available.
PVOCs and naphthalene were not detected in MW-2 and MW-3.
PVOCs and naphthalene were not detected in MW-1 in the last three rounds.
Benzene was detected at 1.78 ppb in MW-1 in the first round.
AV status report and a fee of $700.00 will be submitted in accordance with the Wis. Stats. ch. 292.55 (1) (d) (3) to determine the adequacy of the environmental investigation prior to submitting the SIR and closure.
|