Reporting Period: | 1/1/2023 - 6/30/2023 |
BRRTS No: | 02-41-278106 |
Activity Name: | COLONY DRY CLEANERS FMR |
Status: | Site Investigation |
Activity: | Field Sampling/Monitoring |
Comments: | An NR 716 compliant Site Investigation Report was submitted on April 18, 2023. The WDNR did not approve the SIR and requested additional soil, groundwater and sub-slab vapor sampling and analysis in a letter dated June June 2, 2003. UEC is preparing a budget to perform the requested investigative activities for WDNR review and approval prior to their initiation to maintain DERF eligibility. |
Submitted by Timothy J. Anderson - United Engineering Consultants on 07/30/2023 |