Comments: |
Revised Remedial Action Plan submitted July 22, 2023
Pre-Design Investigation work completed by Tetra Tech on behalf of Beazer included:
⢠Depot Road Soil Investigation with data submittals on Oct 10, 2023; Nov 21, 2023; and Dec 18, 2023
⢠Horizontal and vertical delineation of DNAPL extent on Connell property
⢠Initiated ISS Treatability Study
⢠Groundwater sampling event in December 2023
Pre-Design Investigation work completed by Ramboll on behalf of Connell included:
⢠Supplemental PCB sampling for soil, concrete and asphalt.
⢠Round of groundwater sampling for PCBs and metals.
⢠A data memo with the results of this sampling will be submitted in January 2024
|