ENVIRONMENTAL CLEANUP & BROWNFIELDS REDEVELOPMENT
NR700 ACTIVITY PROGRESS REPORT

Reporting Period: 7/1/2023 - 12/31/2023
BRRTS No: 02-08-587108
Activity Name: HARP DOWNSTREAM OF HAYTON MILLPOND DAM
Status: Site Investigation
Activity: Field Sampling/Monitoring
Comments: Significant source removal and restoration efforts have been completed upstream and received No Further Action determinations. The site investigation activities were completed between July and October 2023 in accordance with the WDNR-approved Site Investigation Work Plan.
Submitted by Chris Harvey on 01/17/2024