NR700 ACTIVITY PROGRESS REPORT

Reporting Period: 1/1/2024 - 6/30/2024
BRRTS No: 02-16-580678
Activity Name: MUNGER LANDING
Status: Remediation
Activity: Closure Request Package Preparation
Comments: The Munger Landing Great Lakes Legacy Act project began construction in July 2022. Excavation/Dredging began in August 2022 and was completed in September 2023. Approximately 107,200 cubic yards of sediment were dredged and disposed of offsite. Residual capping operations began in August 2023 and continued through December 2023. Approximately 70,200 cubic yards of sand were placed followed by 9,200 cubic yards of Biomedium material. Restoration activities began in December 2023 and were completed in June 2024. Post construction sampling has been completed and the contractor is working on closeout documentation. The Wisconsin Department of Natural Resources (WDNR), Minnesota Pollution Control Agency (MPCA), and Paramount Global are collaborating as non-federal sponsors of the project. Paramount Global anticipates filing a BRTTS closure request to the WDNR upon completion of remedial activities.
Submitted by Jim Hutchens on 07/08/2024