Reporting Period: | 7/1/2014 - 12/31/2014 |
BRRTS No: | 02-05-217270 |
Activity Name: | ONE HOUR MARTINIZING |
Status: | Site Investigation |
Activity: | Field Sampling/Monitoring |
Comments: | As requested by WDNR, vapor pathway mapping occurred in mid-2014. WDNR requested development of work plan for vapor assessment. work plan was submitted to owner in draft. |
Submitted by Bob Mottl on 02/01/2015 |