Comments: |
Pre-Design Investigation work completed by Tetra Tech on behalf of Beazer included:
1. A DNAPL Delineation Report was submitted on Feb 15, 2024, and a revised report was submitted on Mar 8, 2024
2. Depot Road Soil Investigation with data submittals on Feb 9, 2024, and Mar 18, 2024
3. Work continued on ISS Treatability Study
4. Groundwater sampling of repaired well MW-116 was completed on Apr 2, 2024
Pre-Design Investigation work completed by Ramboll on behalf of Connell included:
1. Pre-design Data Technical Memorandum dated Jan 19, 2024
2. Conducted Spring 2024 pre-remedial groundwater sampling
NR 724 Remedial Design Report
1. Both Beazer and Connell groups are making progress toward completing the joint NR 724 Remedial Design Report and its Attachments.
|