ENVIRONMENTAL CLEANUP & BROWNFIELDS REDEVELOPMENT
NR700 ACTIVITY PROGRESS REPORT

Reporting Period: 1/1/2024 - 6/30/2024
BRRTS No: 02-38-580694
Activity Name: JCI/TYCO FTC (PFAS)
Status: Site Investigation
Activity: Field Sampling/Monitoring
Comments: A Q4 2023 Project Status report was submitted on January 16. Ditch A, Ditch B, and Groundwater Extraction and Treatment System (GETS) Monthly Wisconsin Pollution Discharge Elimination System (WPDES) Discharge Monitoring Reports (December 2023) were submitted on January 19. A 2023 Foam Monitoring Interim Action Report was submitted on February 16. A Surface Water Advisory Sign Installation Memo was submitted on February 21. Ditch A, Ditch B, and GETS Monthly WPDES Discharge Monitoring Reports (January 2024) were submitted on February 21. A Modification to GETS under WPDES General Permit no. WI-0046566-07-0 was submitted on February 29. A Deep Private Well Quarterly Update – Q1 2024 was submitted on March 1. A GETS Lab Report Appendix was submitted on March 3. A Revised Materials Management Plan was submitted on March 5. An Interim Long Term Groundwater Monitoring Plan was submitted on March 15. Ditch A, Ditch B, and GETS Monthly WPDES Discharge Monitoring Reports (February 2024) were submitted on March 21. A Quality Assurance Project Plan (QAPP) was submitted on March 29. A Deep Aquifer Bedrock Well Design and Long-Term Monitoring Work Plan – Interim Action Status Update was submitted on April 1. A Revised Comprehensive Alternative Water Management Plan was submitted on April 1. A Revised Long-Term Potable Well Sampling Plan, v.9 was submitted on April 1. A Q1 2024 Project Status report was submitted on April 15. Ditch A, Ditch B, and GETS Monthly WPDES Discharge Monitoring Reports (March 2024) were submitted on April 19. A Ditch B Semi-Annual Operation, Maintenance, and Optimization Progress Report #9 was submitted on April 22. A Ditch A Semi-Annual Operation, Maintenance, and Optimization Progress Report #10 was submitted on April 26. A Deep Aquifer Bedrock Well Design and Long-Term Monitoring Work Plan – Interim Action Status Update was submitted on May 17. Ditch A, Ditch B, and GETS Monthly WPDES Discharge Monitoring Reports (April 2024) were submitted on May 21. A Deep Aquifer Bedrock Well Design and Long-Term Monitoring Update – Quarterly Deep Private Well Update (March – May 2024) was submitted on May 31. A Response to April 17, 2024 Comments – Response to Interim Long Term Monitoring Plan for Groundwater and Surface Water was submitted on June 3. A GETS Semi-Annual Monitoring – November 13, 2023 through May 12, 2024 was submitted on June 3. Ditch A, Ditch B, and GETS Monthly WPDES Discharge Monitoring Reports (May 2024) were submitted on June 21. A Response to May 8, 2024 Comments – Response to Revised Comprehensive Alternative Water Management Plan was submitted on June 2. The site investigation work is ongoing. Deep replacement private well installations are ongoing. The Long-Term Potable Well Monitoring Plan is ongoing. Bottled water and/or Point-of-Entry Treatment (POET) systems have been offered to affected potable well owners within the private drinking water well investigation area. The Ditch A and Ditch B Surface Water, Groundwater Extraction and Treatment System, and Foam Interim Actions continued implementation during the reporting period. Routine communications were completed with the WDNR regarding the interim action and site investigation activities.
Submitted by Shauna Johnson on 07/26/2024