NR700 ACTIVITY PROGRESS REPORT

Reporting Period: 7/1/2024 - 12/31/2024
BRRTS No: 02-13-585319
Activity Name: WANG F35 BUILDING CONSTRUCTIONS
Status: Remediation
Activity: No Activity
Comments: The previous 6 months have seen numerous F-35 construction projects come to completion. There has been no soil added to the temporary soil holding pile over the last 6 months. The final F-35 construction project has been awarded (F-35 Construct M&I facility). A materials management plan was submitted to the WI DNR and was subsequently approved for this project. This project is now out of the ground and all soil excavated was able to be re-used on-site. No dewatering has been required. At this time, only the following projects remain under construction. XGFG219012 - F-35 Construct M&I Facility - 15% constructed XGFG179036 - Construct Small Arms Range - 80% constructed
Submitted by Lt Col Michael Dunlap on 01/02/2025