Comments: |
Quarterly discharge monitoring reports for the groundwater remediation system were prepared and submitted to the WDNR. The first quarter 2014 discharge monitoring report was submitted on or about April 1, 2014. The second quarter 2014 discharge monitoring report was submitted on or about July 2, 2014.
The first semi-annual groundwater sampling round was performed in May 2014. The results of the first semi-annual groundwater sampling round will be included in the annual progress report for the site.
|