Comments: |
- The facility submitted the Site Investigation Summary Report (SISR) on November 1, 2024. This report covered the groundwater monitoring event that was completed August 12 - 14, 2024. The sampling was completed in general accordance with the WDNR approved work plan, 2024 PFAS Site Investigation Work Plan, dated July 8, 2024 (2024 SIWP). The SISR submitted on November 1, 2024, summarized the results for the 2024 Q3 groundwater PFAS sampling and included a summary of the field activities and groundwater analytical results. The report also proposed another round of sampling to be completed in Q3 2025.
- The results of the sampling completed from August 12 - 14, 2024 were submitted to the WDNR on September 18, 2024.
|