Comments: |
An updated Remedial Action Plan (RAP) was submitted to WDNR on February 11, 2015 and approved by WDNR on April 17, 2015. Fehr Graham proposes to conduct a
remedial excavation with subsequent soil sampling and two quarters of postâexcavation groundwater monitoring at this property. The purpose of the updated RAP was to summarize findings from additional sampling completed at the site in
2012 after award of the Remedial Action to Alpha Terra Science (now Fehr Graham), and to present the remaining actions to be completed in the previously approved RAP to bring this site to case closure.
Fehr Graham plans to conduct the remedial excavation end of July 2015 with subsequent monitoring and reporting thereafter.
|