Comments: |
2014 Annual monitoring report submitted to WDNR in May 2015. 2015 report will be submitted in first quarter 2016.
A technical assistance request was submitted to WDNR on August 31, 2015 regarding operational recommendations in the 2014 report. Response from the WDNR was received October 26, 2015 granting conditional approval of the recommendations.
Work at the site continues to include routine operation/maintenance of the SVE/LFG system and routine annual and semi-annual groundwater and residential well monitoring.
|