Comments: |
Advanced 6 soil borings in August. Collected and analyzed two soil
samples per boring for VOCs.
Collected groundwater levels and samples from monitoring well
network in July and October for VOCs and PAHs. One additional sample was
collected from well MW- 3 in December. The monitoring well network includes
7 wells.
Collect three sub-slab vapor samples from under the site building in
August.
Collected three indoor air samples co-located with the three
sub-slab vapor samples in September.
Completed site walk to review potential locations for vapor
intrusion in October.
Collected tetrachloroethene dragger tube samples in building in
December.
Completed a site walk to review onsite chemical usage in December.
|