Wisconsin Department of Natural Resources Drinking Water System Routine Monitoring Requirements Period: 01/01/2026 to 12/31/2026 Subject to change -- based on information provided to DNR as of 11/16/2026 Attachment 1 11/16/2026 06:27:32 AM

If any of the following information has changed, please contact your DNR representative with any corrections:
AVALOS, ALEJANDRO LA CROSSE, WI 54601
Phone: (608) 790-5907 Email: ALEJANDRO.AVALOS@WISCONSIN.GOV

System Name: PRAIRIE DU CHIEN WATERWORKS PWS ID#: 61202504 Population: 6,005

Sampler: LEAD WATER OPER BILL RODENKIRCH Owner: CITY CLERK TINA FULLER

The following is a table of the routine monitoring required for this water system (additional monitoring may be required based on results of this monitoring). Each row represents a DNR monitoring requirement. Failure to complete a requirement may result in a monitoring violation. Please make sure that you are using the correct lab sheet for each sample, based on the correct time period, sample location and sample group.

Completed? Monitoring Period Sample Source Sample Group # of samples # of contams
COMPLETEJANUARYDistributionColiform Bacteria71
COMPLETEJANUARY - MARCH1 RawColiform Bacteria11
COMPLETEJANUARY - MARCH3 RawColiform Bacteria11
COMPLETEJANUARY - MARCH4 RawColiform Bacteria11
COMPLETEJANUARY - SEPTEMBEREP 1Inorganics126
COMPLETEJANUARY - SEPTEMBEREP 3Inorganics126
COMPLETEJANUARY - SEPTEMBEREP 4Inorganics126
COMPLETEJANUARY - SEPTEMBEREP 1Radioactivity - Grab14
COMPLETEJANUARY - SEPTEMBEREP 3Radioactivity - Grab14
COMPLETEJANUARY - SEPTEMBEREP 4Radioactivity - Grab14
COMPLETEJANUARY - SEPTEMBEREP 4Synthetic Organics12
COMPLETEJANUARY - SEPTEMBEREP 1Volatile Organics121
COMPLETEJANUARY - SEPTEMBEREP 3Volatile Organics121
COMPLETEJANUARY - SEPTEMBEREP 4Volatile Organics121
COMPLETEFEBRUARYDistributionColiform Bacteria71
COMPLETEMARCHDistributionColiform Bacteria71
COMPLETEAPRILDistributionColiform Bacteria71
COMPLETEAPRIL - JUNE1 RawColiform Bacteria11
COMPLETEAPRIL - JUNE3 RawColiform Bacteria11
COMPLETEAPRIL - JUNE4 RawColiform Bacteria11
COMPLETEMAYDistributionColiform Bacteria71
COMPLETEJUNEDistributionColiform Bacteria71
COMPLETEJUNE - SEPTEMBERDistributionLead and copper202
COMPLETEJULYDistributionColiform Bacteria71
COMPLETEJULY - SEPTEMBER1 RawColiform Bacteria11
COMPLETEJULY - SEPTEMBER3 RawColiform Bacteria11
COMPLETEJULY - SEPTEMBER4 RawColiform Bacteria11
COMPLETEJULY - SEPTEMBERDistributionDisinfection Byproducts (TTHM, HAA5)111
COMPLETEJULY - SEPTEMBEREP 1Per/Poly-Fluoroalkyls (PFAS)16
COMPLETEAUGUSTDistributionColiform Bacteria71
COMPLETEAUGUST - AUGUST1Coliform Bacteria11
COMPLETEAUGUST - AUGUST3Coliform Bacteria11
COMPLETEAUGUST - AUGUST4Coliform Bacteria11
COMPLETESEPTEMBERDistributionColiform Bacteria71
COMPLETESEPTEMBEREP 3Per/Poly-Fluoroalkyls (PFAS)16
COMPLETEOCTOBERDistributionColiform Bacteria71
COMPLETEOCTOBEREP 4Per/Poly-Fluoroalkyls (PFAS)16
COMPLETEOCTOBER - DECEMBER3 RawAmmonia11
COMPLETEOCTOBER - DECEMBER4 RawAmmonia11
COMPLETEOCTOBER - DECEMBER1 RawColiform Bacteria11
OCTOBER - DECEMBER3 RawColiform Bacteria11
OCTOBER - DECEMBER4 RawColiform Bacteria11
NOVEMBERDistributionColiform Bacteria71
DECEMBERDistributionColiform Bacteria71
Waivers:
Asbestos (Inorganic Report Form)1Waiver issued - No sampling required during calendar year 2026
Asbestos (Inorganic Report Form)3Waiver issued - No sampling required during calendar year 2026
Asbestos (Inorganic Report Form)4Waiver issued - No sampling required during calendar year 2026
Benzo(A)Pyrene (Synthetic Form)1Waiver issued - No sampling required during calendar year 2026
Benzo(A)Pyrene (Synthetic Form)3Waiver issued - No sampling required during calendar year 2026
Benzo(A)Pyrene (Synthetic Form)4Waiver issued - No sampling required during calendar year 2026
Cyanide (Inorganic Report Form)1Waiver issued - No sampling required during calendar year 2026
Cyanide (Inorganic Report Form)3Waiver issued - No sampling required during calendar year 2026
Cyanide (Inorganic Report Form)4Waiver issued - No sampling required during calendar year 2026
Dioxin (Synthetic Report Form)1Waiver issued - No sampling required during calendar year 2026
Dioxin (Synthetic Report Form)3Waiver issued - No sampling required during calendar year 2026
Dioxin (Synthetic Report Form)4Waiver issued - No sampling required during calendar year 2026
EDB/DBCP (Synthetic Report Form)1Waiver issued - No sampling required during calendar year 2026
EDB/DBCP (Synthetic Report Form)3Waiver issued - No sampling required during calendar year 2026
EDB/DBCP (Synthetic Report Form)4Waiver issued - No sampling required during calendar year 2026
Industrial Chemicals (Synthetic Form)1Waiver issued - No sampling required during calendar year 2026
Industrial Chemicals (Synthetic Form)3Waiver issued - No sampling required during calendar year 2026
Synthetic Organics - Pop < 100001Waiver issued - No sampling required during calendar year 2026
Synthetic Organics - Pop < 100003Waiver issued - No sampling required during calendar year 2026
Synthetic Organics - Pop < 100004Waiver issued - No sampling required during calendar year 2026