CITY OF STEVENS POINT: McDill Pond Sediment Control Strategies Planning
The City of Stevens Point proposes to complete the last phase of a comprehensive lake management plan for McDill Pond. Project activities include 1) model sediment loading to lake and evaluate sediment basin, 2) determine pollutant loading from stormwater sources, 3) bring study results and recommendations to the public, and 4) begin writing comprehensive plan for lake. A final report will be prepared detailing the project results. Information on the project results will be disseminated to the public by newsletter mailing, fact sheet distribution, public meeting, and local newspaper article.
Project Type
|
LAKE_GRANT
-
Large Scale Lake Planning
|
Project ID
|
LPL-379
|
Year Started
|
1996
|
Status
|
COMPLETE
|
Activities
- Water Quality Modeling
- Informational Meetings
- Issue News/Media Release
- Lake Management Plan Development
- Develop/Distribute Brochures/Literature
Final Report and Products