CITY OF BLOOMER: Lake Como Management Plan, Phase I
The City of Bloomer proposes to develop a management plan for Lake Como, in part, to determine whether the maintain the lake and, if so, how to improve the water quality. Phase One project activities to include: 1) Development and use of public Needs Assessment Questionaire, 2) two formal public hearings, 3) update and completion of cost estimates for options including dam removal, dam repair, and upgrading the dam to meet high hazard standards, 4) preparation of a decision matrix (decision and project timeline), 5) development of floodplain mitigation plan, 6) development of park plan.
Project Type
|
LAKE_GRANT
-
Large Scale Lake Planning
|
Project ID
|
LPL-626
|
Year Started
|
1999
|
Status
|
COMPLETE
|
Activities
- Lake Management Plan Development
Final Report and Products