Anvil Lake Association, Inc. is sponsoring phase 2 of an Early Detection and Response project to be completed by December 31, 2017. The project will focus on surveying, mapping and hand-pulling the new discovery of EWM in Anvil Lake, Vilas County.
Project activities include: 1) Conduct annual early-season AIS and peak-biomass surveys; 2) Conduct early season acoustic survey; 3) Control EWM by hand removal efforts; 4) Develop annual maps and letter report.
Project deliverables include: 1) EWM survey data and maps; 2) Annual letter report describing the findings of the early-spring survey, peak-biomass survey, acoustic survey, hand-pulling efforts, and guidance for continued control actions.
Specific conditions for this project: Annual letter report needs Dept review and approval.
WDNR Lakes Management Coordinator will be provided with an electronic (pdf or word) copy of letter reports, all maps, and all aquatic plant and GIS data.
Project Type
|
AIS_GRANT
-
Aquatic Invasives Early Detection and Response
|
Project ID
|
AIRR-177-15
|
Year Started
|
2013
|
Status
|
COMPLETE
|
Activities
- Aquatic Plant Monitoring or Survey
- APM Mechanical Permit Request
- Monitor Invasive Species
- Project Deliverable
Final Report and Products