LAKESHORE NATURAL RESOURCES PARTNERSHIP INC.: LMI-Carstens Lake Hill Line Dairy Sedimentation Basin
Lakeshore Natural Resources Partnership (LNRP) is sponsoring a project to begin implementing their 2017 Carstens Lake Comprehensive Management Plan to improve water quality in
Project final deliverables include: all design plans and a final report summarizing the project.
Specific project activities include: 1) Develop a concept plan for an off-line sedimentation basin adjacent to Pine Creek upstream of Carstens Lake; 2) Design the sedimentation basin per agreed upon concept along with an operation and maintenance plan; 3) Construct the sedimentation basin; 4) Install a perennial vegetated buffer adjacent to the sedimentation basin; 5) Conduct an aquatic plant survey and develop a report with aquatic plant management recommendations for Carstens Lake.
Special Conditions: 1) Prior to construction, LNRP will obtain all requisite landowner access and permits as required from WDNR, the US Army Corps of Engineers (USACOE), Manitowoc County, and other regulatory agencies or municipalities.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Lakes Biologist.
If consultant is to provide final report, it is recommended that Grantee provide DNR Rivers Coordinator with a draft for comment on report adequacy prior to making final payment to the consultant. DNR to receive both paper and electronic .pdf copies of the final report along with, or prior to submission of grantee's final payment request.
Project Type
|
LAKE_GRANT
-
Lake Protection Grant
|
Project ID
|
LPT57218
|
Year Started
|
2018
|
Status
|
ACTIVE
|