TOWN OF GENEVA: Lake Como AIS Survey & APM Update
The Town of Geneva will hire a contractor to conduct a plant survey and update the aquatic plant management plan for Lake Como. The plant survey will be a point intercept survey with XY points. The lake will be sampled in mid-summer. The final report will contain the following elements: 1) Results of the points sampled, including sediment type found and maximum rooting depth, 2) Results of a general lake survey to map general plant beds, map localized plant beds, map species distribution and a list of plant species found, 3) An aquatic plant management plan that meets the requirements of NR 109.09, 4) GIS mapping of control areas, and 5) Evaluation of the use of chemical control measures for invasive plant species. 10 copies of the report will be provided to the Town.
Project Type
|
AIS_GRANT
-
Aquatic Invasives Education
|
Project ID
|
AEPP-201-10
|
Year Started
|
2009
|
Status
|
COMPLETE
|
Activities
- Aquatic Plant Monitoring or Survey