LAKE REDSTONE PROTECTION DISTRICT: RES - Chickadee So. Sediment Reduction Project\005C00A0
The Lake Redstone Protection District is sponsoring a sediment reduction project in Chickadee bay of Lake Redstone by creating a sediment basin with a controlled outlet structure.
Project final deliverables include:
1. Creation of a sediment basin with a controlled outlet structure.
2. A final report detailing reductions in total suspended solids (TSS) documented with the model WinSLAMM. reductions in total phosphorus (TP) using the model PRESTO, and before & after photos will be sent to the regional lakes coordinator (Arthur.watkinson@wisconsin.gov) and the environmental grants specialist (gina.keenan@wisconsin.gov).
Specific project activities include:
A sediment basin will be excavated; A controlled outlet structure will be installed; WinSLAMM and PRESTO models will be used to document reductions in TSS and TP.
Special Conditions:
All permits must be issued before construction, and all regulatory requirements apply. The project will require a standard Operation and Maintenance agreement of 20 years.
This scope summarizes the project detail provided in the application and does not negate tasks/deliverables described therein. Data, records, and reports, including GIS-based maps, and digital images, must be submitted to the Department in a format specified by the regional Lake Biologist.
Project Type
|
LAKE_GRANT
-
Lake Protection Grant
|
Project ID
|
LPT79623
|
Year Started
|
2023
|
Status
|
ACTIVE
|